Overview
ORBIT CITY
Roop Singh · Sahibzada Ajit Singh Nagar (Mohali)
Units212
Booked0 of 212As of 2026-09-30
Completion2028-05-30Proposed
Registered on2024-07-18
Valid to2028-05-30
Approvals12
Sections
| Property title & search report | |
|---|---|
| Approvals | 12 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 27 unit types |
| Construction & progress | 2 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 29 documents · 24 source links |
Registration
Registration
| Promoter | Roop Singh | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR1028 | |
| Registered on | 2024-07-18 | |
| Valid to | 2028-05-30 | |
| Project type | (1) Commercial (Plotted Development) (2) Residential (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2028-05-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2024-03-11 | |
| CLU Certificate | ||
| Electric Substation NOC | 2024-04-09 | |
| Environment Clearance certificate/ NOC | Legal Documents (Received) | 2023-05-19 |
| License as Promoter from competent Authority | 2023-08-21 | |
| License to develop colony or society from Competent Authority | ||
| NOC from NHAI/ PWD | 2024-03-11 | |
| Other Document (Affidavit NOC) | Legal Documents (Received) | 2024-04-30 |
| Other Document (Drainage NOC) | 2023-10-13 | |
| Other Document (Forest NOC) | 2023-12-04 | |
| Other Document (Solid Waste NOC) | 2024-02-26 | |
| Pollution Clearance from Punjab Pollution Control Board | 2023-10-08 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹9,18,15,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 33,290 | |
|---|---|---|
| Units | 212 | |
| Booked | 0 | |
| Booked as of | 2026-09-30 |
Unit types
| Plot No. 106-114 | 106.877 | 9 | 0 | RESIDENTIAL PLOTS |
| Plot No. 115-139 | 105.808 | 25 | 0 | RESIDENTIAL PLOTS |
| Plot No. 140-149 | 102.602 | 10 | 0 | RESIDENTIAL PLOTS |
| Plot No. 174 and 196 | 88.801 | 2 | 0 | RESIDENTIAL PLOTS |
| Plot No. 175-195 | 86.687 | 21 | 0 | RESIDENTIAL PLOTS |
| Plot No. 197-206 | 125.465 | 10 | 0 | RESIDENTIAL PLOTS |
| Plot No. 1-4 | 125.012 | 4 | 0 | RESIDENTIAL PLOTS |
| Plot No. 9 and 10 | 105.901 | 2 | 0 | RESIDENTIAL PLOTS |
| Plot No. 5-8, 11-14 | 103.439 | 8 | 0 | RESIDENTIAL PLOTS |
| Plot No. 15-18 | 89.777 | 4 | 0 | RESIDENTIAL PLOTS |
| Plot No. 19 | 109.015 | 1 | 0 | RESIDENTIAL PLOTS |
| Plot No. 20 | 107.83 | 1 | 0 | RESIDENTIAL PLOTS |
| Plot No. 21-42 | 84.572 | 22 | 0 | RESIDENTIAL PLOTS |
| Plot No. 43 | 88.801 | 1 | 0 | RESIDENTIAL PLOTS |
| Plot No. 44-72 | 103.671 | 29 | 0 | RESIDENTIAL PLOTS |
| Plot No. 73-76, 79-82 | 97.584 | 8 | 0 | RESIDENTIAL PLOTS |
| Plot No. 77,78,87,88 | 99.907 | 4 | 0 | RESIDENTIAL PLOTS |
| Plot No. 83-86, 89-92 | 97.584 | 8 | 0 | RESIDENTIAL PLOTS |
| Plot No. 93-96 | 88.754 | 4 | 0 | RESIDENTIAL PLOTS |
| Plot No. 97 | 90.915 | 1 | 0 | RESIDENTIAL PLOTS |
| Plot No. 98 | 113.847 | 1 | 0 | RESIDENTIAL PLOTS |
| Plot No. 99-105 | 125.465 | 7 | 0 | RESIDENTIAL PLOTS |
| Plot No. 150 and 163 | 78.81 | 2 | 0 | EWS RESIDENTIAL PLOTS |
| Plot No. 151-162 | 81.273 | 12 | 0 | EWS RESIDENTIAL PLOTS |
| Plot No. 164-168 | 63.429 | 5 | 0 | EWS RESIDENTIAL PLOTS |
| Plot No. 169-173 | 80.344 | 5 | 0 | EWS RESIDENTIAL PLOTS |
| Plot No. 1-6 | 27.881 | 6 | 0 | COMMERCIAL PLOTS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-01-10 | |
|---|---|---|
| Proposed completion | 2028-05-30 |
Quarterly progress
| 2024-Q3 | 2024-10-12 | ||
| 2024-Q4 | 2025-01-13 | ||
| 2025-Q1 | 2025-04-15 | ||
| 2025-Q2 | 2025-07-15 | ||
| 2025-Q3 | 2025-10-21 | ||
| 2025-Q4 | 2026-01-15 | ||
| 2026-Q1 | 2026-04-12 | ||
| 2026-Q2 | 2026-07-14 | ||
| 2026-Q3 | 2026-10-13 | 0 | 0 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Roop Singh | |
|---|---|---|
| Type | Individual | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Architect | CHAMAN AND ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectQuarterlyUpdateViewDetails?inProject_ID=11866&inPromoter_ID=2600&inPromoterType=11866&inQUProject_ID=6588&inQUProject_DN=QUP2026T20266588&inQUProjectYear=2026&inQUProjectQTR=ThirdQTR
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11866&inPromoter_ID=2600&inPromoterType=1
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2024-03-11
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2024-04-09
- Environment Clearance certificate/ NOC · 2023-05-19
- License as Promoter from competent Authority · 2023-08-21
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2024-03-11
- Other Document (Drainage NOC) · 2023-10-13
- Other Document (Forest NOC) · 2023-12-04
- Other Document (Solid Waste NOC) · 2024-02-26
- Pollution Clearance from Punjab Pollution Control Board · 2023-10-08
- Consent details of actual owner of Land · Sign in to download
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Annual Report (Form-5 CA Certificate)
- Pollution Clearance from Punjab Pollution Control Board · 2026-07-08
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2024-03-11
- CLU Certificate
- Electric Substation NOC · 2024-04-09
- Environment Clearance certificate/ NOC · 2023-05-19
- License as Promoter from competent Authority · 2023-08-21
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2024-03-11
- Other Document (Affidavit NOC) · 2024-04-30
- Other Document (Drainage NOC) · 2023-10-13
- Other Document (Forest NOC) · 2023-12-04
- Other Document (Solid Waste NOC) · 2024-02-26
- Pollution Clearance from Punjab Pollution Control Board · 2023-10-08
- 2024-Q3 · 2024-10-12
- 2024-Q4 · 2025-01-13
- 2025-Q1 · 2025-04-15
- 2025-Q2 · 2025-07-15
- 2025-Q3 · 2025-10-21
- 2025-Q4 · 2026-01-15
- 2026-Q1 · 2026-04-12
- 2026-Q2 · 2026-07-14