Overview
Orchard Street
Radiant Hotels Private Limited · Jaipur
Units56
Booked26 of 56As of 2026-09-30
Completion2027-04-19Revised · Proposed 2025-08-01
Registered on2025-07-12
Valid to2027-04-19
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 17 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 39 documents · 6 source links |
Registration
Registration
| Promoter | Radiant Hotels Private Limited | |
|---|---|---|
| District | Jaipur | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2025/4014 | |
| Registered on | 2025-07-12 | |
| Valid to | 2027-04-19 | |
| Project type | Plotted | |
| Status (as filed) | INPROGRESS | |
| Proposed completion | 2025-08-01 | |
| Revised completion | 2027-04-19 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹56,96,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹59,31,00,000 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2026-Q3 | ₹24,27,17,800 | ₹23,082.38 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 18,987.62 | |
|---|---|---|
| Built-up (m²) | 11,736.86 | |
| Towers | 56 | |
| Units | 56 | |
| Booked | 26 | |
| Booked as of | 2026-09-30 |
Unit types
| Plot No.- 28,29,30,31 | 4 | 4 |
| Plot No.- 42 | 1 | 1 |
| Informal Commercial | 1 | 0 |
| Plot No.- 21 | 1 | 1 |
| Plot No.- 27,32,33,34,35,36,48,49,50,51,52,53,54,55,56,57 | 16 | 8 |
| Plot No.- 38 | 1 | 0 |
| Plot No.- 39,40 | 2 | 2 |
| Plot No.- 2,3,4,5,6,7,12,13,14,16,16A,18,19,22,23,24,25 | 17 | 11 |
| Plot No.- 26,58 | 2 | 1 |
| Plot No.- 41 | 1 | 1 |
| Plot No.- 8,9 | 2 | 1 |
| Plot No.- 37,47 | 2 | 0 |
| Plot No.- 20 | 1 | 0 |
| Plot No.- 10,11 | 2 | 1 |
| Plot No.- 1 | 1 | 0 |
| Plot No.- 44 | 1 | 0 |
| Plot No.- 43 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-08-01 | |
|---|---|---|
| Proposed completion | 2025-08-01 | |
| Revised completion | 2027-04-19 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2026-Q3 | 2026-10-29 | 26 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Radiant Hotels Private Limited | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Punjab National Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=0gbDqAeLzedqcpeAS6EsuQ
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/0gbDqAeLzedqcpeAS6EsuQ
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=0gbDqAeLzedqcpeAS6EsuQ%3D%3D&QuarterIdEnc=%2BKD7QcnAdOtELCm57RAuQA%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=3Clk4rreHwE%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Others
- Bankaffidavit · Sign in to download
- SitePlanPath · 2025-06-17
- LayoutPlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- SitePlanPath · 2025-06-17
- Site_Plan_Doc_Sanctioned
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_filepath · Sign in to download
- R2_filepath · Sign in to download
- R3_filepath · Sign in to download
- RERABankStatementUpload · Sign in to download
- NoLienCertificateUpload