Overview
OURO HILLS
M/S R.R. DEVELOPERS · RAIGARH
Units119
Booked76 of 119As of 2026-06-30
Construction progress95%As of 2026-06-30
Completion2029-02-18Revised · Proposed 2028-10-18
Registered on2023-11-10
Approvals3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Contract & costs | 2 cost heads · 11 quarters |
| Technical report | |
| Site & area | 3 site details · 119 unit types |
| Construction & progress | 4 progress details · 11 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 81 documents · 6 source links |
Registration
Registration
| Promoter | M/S R.R. DEVELOPERS | |
|---|---|---|
| District | RAIGARH | |
| Regulator | CG RERA | |
| Registration number | PCGRERA101123001700 | |
| Registered on | 2023-11-10 | |
| Project type | Residential Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2028-10-18 | |
| Revised completion | 2029-02-18 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,17,07,000 | |
|---|---|---|
| Construction | ₹7,00,81,000 |
Quarterly money flows
| 2023-Q4 | ₹70,000 |
| 2024-Q1 | ₹1,95,40,982.82 |
| 2024-Q2 | ₹47,73,272.82 |
| 2024-Q3 | ₹2,97,972 |
| 2024-Q4 | ₹16,20,735.39 |
| 2025-Q1 | ₹2,59,133 |
| 2025-Q2 | ₹8,89,103 |
| 2025-Q3 | ₹9,103 |
| 2025-Q4 | ₹8,25,603 |
| 2026-Q1 | ₹9,65,603 |
| 2026-Q2 | ₹20,48,503 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 119 | |
|---|---|---|
| Booked | 76 | |
| Booked as of | 2026-06-30 |
Unit types
| A-1 | 1 | 0 |
| A-2 | 1 | 1 |
| A-3 | 1 | 1 |
| A-4 | 1 | 1 |
| A-5 | 1 | 1 |
| A-6 | 1 | 1 |
| A-7 | 1 | 0 |
| A-8 | 1 | 0 |
| A-9 | 1 | 0 |
| A-10 | 1 | 0 |
| A-11 | 1 | 0 |
| A-12 | 1 | 1 |
| A-13 | 1 | 1 |
| A-14 | 1 | 0 |
| A-15 | 1 | 0 |
| A-16 | 1 | 0 |
| A-17 | 1 | 0 |
| A-18 | 1 | 0 |
| A-19 | 1 | 0 |
| A-20 | 1 | 0 |
| A-21 | 1 | 0 |
| A-22 | 1 | 0 |
| A-23 | 1 | 0 |
| B-1 | 1 | 1 |
| B-2 | 1 | 1 |
| B-3 | 1 | 1 |
| B-4 | 1 | 1 |
| B-5 | 1 | 1 |
| B-6 | 1 | 1 |
| B-7 | 1 | 1 |
| B-8 | 1 | 1 |
| B-9 | 1 | 1 |
| B-10 | 1 | 1 |
| B-11 | 1 | 1 |
| B-12 | 1 | 1 |
| B-13 | 1 | 1 |
| B-14 | 1 | 1 |
| B-15 | 1 | 1 |
| B-16 | 1 | 1 |
| B-17 | 1 | 1 |
| B-18 | 1 | 1 |
| B-19 | 1 | 1 |
| B-20 | 1 | 1 |
| B-21 | 1 | 1 |
| B-22 | 1 | 1 |
| C-1 | 1 | 1 |
| C-2 | 1 | 1 |
| C-3 | 1 | 1 |
| C-4 | 1 | 1 |
| C-5 | 1 | 1 |
| C-6 | 1 | 1 |
| C-7 | 1 | 1 |
| C-8 | 1 | 1 |
| C-9 | 1 | 1 |
| D-1 | 1 | 1 |
| D-2 | 1 | 1 |
| D-3 | 1 | 1 |
| D-4 | 1 | 1 |
| D-5 | 1 | 1 |
| D-6 | 1 | 1 |
| D-7 | 1 | 1 |
| D-8 | 1 | 1 |
| D-9 | 1 | 1 |
| D-10 | 1 | 1 |
| D-11 | 1 | 0 |
| D-12 | 1 | 0 |
| D-13 | 1 | 0 |
| D-14 | 1 | 1 |
| D-15 | 1 | 1 |
| D-16 | 1 | 0 |
| D-17 | 1 | 1 |
| D-18 | 1 | 1 |
| D-19 | 1 | 1 |
| E-1 | 1 | 1 |
| E-2 | 1 | 1 |
| E-3 | 1 | 1 |
| E-4 | 1 | 1 |
| E-5 | 1 | 1 |
| E-6 | 1 | 1 |
| E-7 | 1 | 1 |
| E-8 | 1 | 0 |
| E-9 | 1 | 0 |
| E-10 | 1 | 0 |
| E-11 | 1 | 1 |
| E-12 | 1 | 1 |
| E-13 | 1 | 0 |
| E-14 | 1 | 1 |
| E-15 | 1 | 1 |
| E-16 | 1 | 0 |
| E-17 | 1 | 0 |
| E-18 | 1 | 1 |
| F-1 | 1 | 1 |
| F-2 | 1 | 1 |
| F-3 | 1 | 1 |
| F-4 | 1 | 1 |
| F-5 | 1 | 1 |
| F-6 | 1 | 0 |
| F-7 | 1 | 0 |
| F-8 | 1 | 1 |
| F-9 | 1 | 1 |
| F-10 | 1 | 1 |
| F-11 | 1 | 1 |
| F-LIG-12 | 1 | 1 |
| F-LIG-13 | 1 | 0 |
| F-LIG-14 | 1 | 0 |
| F-LIG-15 | 1 | 0 |
| F-16 | 1 | 0 |
| F-17 | 1 | 0 |
| F-18 | 1 | 0 |
| F-LIG-19 | 1 | 0 |
| F-LIG-20 | 1 | 0 |
| F-LIG-21 | 1 | 0 |
| G-1 | 1 | 0 |
| G-2 | 1 | 0 |
| G-3 | 1 | 0 |
| G-4 | 1 | 1 |
| G-5 | 1 | 0 |
| Comm-1 | 1 | 0 |
| Comm-2 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 95% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2028-10-18 | |
| Revised completion | 2029-02-18 |
Quarterly progress
| 2023-Q4 | 0% |
| 2024-Q1 | 20% |
| 2024-Q2 | 50% |
| 2024-Q3 | 55% |
| 2024-Q4 | 60% |
| 2025-Q1 | 80% |
| 2025-Q2 | 90% |
| 2025-Q3 | 90% |
| 2025-Q4 | 90% |
| 2026-Q1 | 90% |
| 2026-Q2 | 95% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M/S R.R. DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MjA4OA==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- Development Cost Description · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities