Overview
OVERSEAS PALM RESORTS
M/S AGRAWAL CONSTRUCTION AND CONTRACTORS · RAIPUR
Units156
Booked107 of 156As of 2022-06-30
Construction progress100%As of 2022-06-30
Completion2022-09-02Revised · Proposed 2020-12-03
Registered on2018-02-24
Approvals2
Cases29
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Disputes & cases | 29 cases |
| Contract & costs | 2 cost heads · 16 quarters |
| Technical report | |
| Site & area | 3 site details · 4 unit types |
| Construction & progress | 4 progress details · 16 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 156 documents · 35 source links |
Registration
Registration
| Promoter | M/S AGRAWAL CONSTRUCTION AND CONTRACTORS | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA240218000002 | |
| Registered on | 2018-02-24 | |
| Project type | Group Housing | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2020-12-03 | |
| Revised completion | 2022-09-02 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| M-PRO-2026-03452 | CG RERA | Complaint | Disposed | 2026-04-27 |
| M-PRO-2026-03445 | CG RERA | Complaint | Disposed | 2026-01-21 |
| M-PRO-2023-01922 | CG RERA | Complaint | Disposed | 2025-02-05 |
| M-PRO-2023-01923 | CG RERA | Complaint | Disposed | 2025-02-05 |
| M-PRO-2024-02328 | CG RERA | Complaint | Disposed | 2024-07-05 |
| M-PRO-2024-02329 | CG RERA | Complaint | Disposed | 2024-07-05 |
| M-PRO-2024-02330 | CG RERA | Complaint | Disposed | 2024-07-05 |
| M-PRO-2024-02335 | CG RERA | Complaint | Disposed | 2024-07-05 |
| M-PRO-2023-02016 | CG RERA | Complaint | Disposed | 2024-04-29 |
| M-PRO-2023-01906 | CG RERA | Complaint | Disposed | 2024-04-22 |
| M-PRO-2023-01907 | CG RERA | Complaint | Disposed | 2024-04-22 |
| M-PRO-2021-01335 | CG RERA | Complaint | Disposed | 2023-11-24 |
| M-PRO-2022-01847 | CG RERA | Complaint | Disposed | 2023-09-20 |
| M-PRO-2022-01843 | CG RERA | Complaint | Disposed | 2023-09-20 |
| M-PRO-2022-01844 | CG RERA | Complaint | Disposed | 2023-09-20 |
| M-PRO-2023-01881 | CG RERA | Complaint | Disposed | 2023-09-20 |
| M-PRO-2023-01870 | CG RERA | Complaint | Disposed | 2023-09-20 |
| M-PRO-2021-01334 | CG RERA | Complaint | Disposed | 2023-09-13 |
| M-PRO-2022-01842 | CG RERA | Complaint | Disposed | 2023-07-05 |
| M-PRO-2023-01887 | CG RERA | Complaint | Disposed | 2023-07-03 |
| M-PRO-2023-01884 | CG RERA | Complaint | Disposed | 2023-07-03 |
| M-REA-2023-01875 | CG RERA | Complaint | Disposed | 2023-06-26 |
| M-PRO-2022-01851 | CG RERA | Complaint | Disposed | 2023-06-23 |
| M-PRO-2022-01841 | CG RERA | Complaint | Disposed | 2023-06-23 |
| M-PRO-2022-01846 | CG RERA | Complaint | Disposed | 2023-02-01 |
| M-PRO-2022-01845 | CG RERA | Complaint | Disposed | 2023-02-01 |
| M-PRO-2021-01374 | CG RERA | Complaint | Disposed | 2021-10-18 |
| M-PRO-2021-01373 | CG RERA | Complaint | Disposed | 2021-10-18 |
| M-COM-2019-00355 | CG RERA | Complaint | Disposed | 2019-05-02 |
Complaints & cases
| Cases | 29 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,44,38,000 | |
|---|---|---|
| Construction | ₹24,27,67,000 |
Quarterly money flows
| 2018-Q3 | ₹33,92,602 |
| 2018-Q4 | ₹10,00,547 |
| 2019-Q1 | ₹42,694 |
| 2019-Q2 | ₹6,52,598 |
| 2019-Q3 | ₹15,34,331 |
| 2019-Q4 | ₹22,18,762 |
| 2020-Q1 | ₹3,52,304 |
| 2020-Q2 | ₹36,684 |
| 2020-Q3 | ₹6,653 |
| 2020-Q4 | ₹49,97,956 |
| 2021-Q1 | ₹3,39,190 |
| 2021-Q2 | ₹25,22,372 |
| 2021-Q3 | ₹46,172 |
| 2021-Q4 | ₹1,705 |
| 2022-Q1 | ₹15,86,925 |
| 2022-Q2 | ₹24,60,496 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 156 | |
|---|---|---|
| Booked | 107 | |
| Booked as of | 2022-06-30 |
Unit types
| 2BHK | 59.9 | 126 | 78 |
| 3BHK | 85.99 | 9 | 9 |
| 3BHK | 77.76 | 10 | 9 |
| 3BHK | 75.54 | 11 | 11 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2022-06-30 | |
| Proposed completion | 2020-12-03 | |
| Revised completion | 2022-09-02 |
Quarterly progress
| 2018-Q3 | 14% |
| 2018-Q4 | 4% |
| 2019-Q1 | 8% |
| 2019-Q2 | 11% |
| 2019-Q3 | 0% |
| 2019-Q4 | 31% |
| 2020-Q1 | 0% |
| 2020-Q2 | 47% |
| 2020-Q3 | 52% |
| 2020-Q4 | 72% |
| 2021-Q1 | 56% |
| 2021-Q2 | 63% |
| 2021-Q3 | 77% |
| 2021-Q4 | 92% |
| 2022-Q1 | 100% |
| 2022-Q2 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M/S AGRAWAL CONSTRUCTION AND CONTRACTORS | |
|---|---|---|
| Type | Other | |
| Escrow bank | DCB Bank | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_completed.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=Mg==
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Building Permission from local Authority
- Project Specifications · Sign in to download
- Apartment Details · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- Engineer Certificate
- CA Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2026-04-27 · Sign in to download
- Final order · 2026-01-21 · Sign in to download
- Final order · 2025-02-05 · Sign in to download
- Final order · 2025-02-05 · Sign in to download
- Final order · 2024-07-05 · Sign in to download
- Final order · 2024-07-05 · Sign in to download
- Final order · 2024-07-05 · Sign in to download
- Final order · 2024-07-05 · Sign in to download
- Final order · 2024-04-29 · Sign in to download
- Final order · 2024-04-22 · Sign in to download
- Final order · 2024-04-22 · Sign in to download
- Final order · 2023-11-24 · Sign in to download
- Final order · 2023-09-20 · Sign in to download
- Final order · 2023-09-20
- Final order · 2023-09-20 · Sign in to download
- Final order · 2023-09-20 · Sign in to download
- Final order · 2023-09-20 · Sign in to download
- Final order · 2023-09-13 · Sign in to download
- Final order · 2023-07-05 · Sign in to download
- Final order · 2023-07-03 · Sign in to download
- Final order · 2023-07-03 · Sign in to download
- Final order · 2023-06-26 · Sign in to download
- Final order · 2023-06-23 · Sign in to download
- Final order · 2023-06-23 · Sign in to download
- Final order · 2023-02-01 · Sign in to download
- Final order · 2023-02-01 · Sign in to download
- Final order · 2021-10-18 · Sign in to download
- Final order · 2021-10-18
- Final order · 2019-05-02 · Sign in to download
- Interim order · 2023-02-06 · Sign in to download
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- M-PRO-2026-03452 · Sign in to download
- M-PRO-2026-03445 · Sign in to download
- M-PRO-2023-01922 · Sign in to download
- M-PRO-2023-01923 · Sign in to download
- M-PRO-2024-02328 · Sign in to download
- M-PRO-2024-02329 · Sign in to download
- M-PRO-2024-02330 · Sign in to download
- M-PRO-2024-02335 · Sign in to download
- M-PRO-2023-02016 · Sign in to download
- M-PRO-2023-01906 · Sign in to download
- M-PRO-2023-01907 · Sign in to download
- M-PRO-2021-01335 · Sign in to download
- M-PRO-2022-01847 · Sign in to download
- M-PRO-2022-01844 · Sign in to download
- M-PRO-2023-01881 · Sign in to download
- M-PRO-2023-01870 · Sign in to download
- M-PRO-2021-01334 · Sign in to download
- M-PRO-2022-01842 · Sign in to download
- M-PRO-2023-01887 · Sign in to download
- M-PRO-2023-01884 · Sign in to download
- M-REA-2023-01875 · Sign in to download
- M-PRO-2022-01851 · Sign in to download
- M-PRO-2022-01841 · Sign in to download
- M-PRO-2022-01846 · Sign in to download
- M-PRO-2022-01845 · Sign in to download
- M-PRO-2021-01374 · Sign in to download
- M-COM-2019-00355 · Sign in to download