Overview
P. P. GREEN CITY
A P REAL ESTATES · Sonipat
Units214
Completion2024-09-09Proposed
Valid to2024-09-09
Approvals9
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Disputes & cases | 1 case · 2 registration details |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 4 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 5 documents · 3 source links |
Registration
Registration
| Promoter | A P REAL ESTATES | |
|---|---|---|
| District | Sonipat | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-SNP-228-2021 | |
| Valid to | 2024-09-09 | |
| Status (as filed) | Lapsed Project | |
| Proposed completion | 2024-09-09 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | License No. 106 of 2019 dated 10.09.2019 (Valid upto 09.09.2024) | Town & Country Planning Department | |
| Layout Plan | |||
| Building Plan | |||
| I. LICENSE NO. 106 OF 2019 | 2019-09-10 | ||
| II. NOC FROM HSPCB (CTE) | 2020-12-12 | ||
| III. APPROVAL OF TEMPORARY SITE OFFICE | 2020-12-17 | ||
| IV. NOC FROM FOREST | 2020-12-04 | ||
| V. APPLICATION FOR PERMISSION TO ABSTRACT GROUND WATER FOR INFRASTRUCTURAL USE | 2020-10-20 | ||
| VI. APPLICATION FOR APPROVAL OF SERVICE PLAN & ESTIMATES | 2020-12-02 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Status |
|---|---|---|
| RERA-PKL-1989-2022 | HRERA Panchkula | Disposed |
Complaints & cases
| Cases | 1 |
|---|
Registration status
| Status | Lapsed Project | |
|---|---|---|
| Valid to | 2024-09-09 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹12,72,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹31,60,55,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 1 | |
|---|---|---|
| Units | 214 |
Unit types
| Plot | 186 | |
| Plot | 27 | |
| Plot | 1 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-01-10 | |
|---|---|---|
| Proposed completion | 2024-09-09 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | A P REAL ESTATES | |
|---|---|---|
| Escrow bank | YES BANK LIMITED | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/SFJFUkEtUEtMLVNOUC0yMjgtMjAyMQ==
- https://haryanarera.gov.in/view_project/project_preview_open/1522
- Registration Certificate
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2021-01-07
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2021-01-07
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2021-01-07
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2021-01-08 · Sign in to download