Overview
PALM RESORTS
M/S AGRAWAL CONSTRUCTION AND CONTRACTORS · RAIPUR
Units76
Booked53 of 76As of 2025-06-30
Construction progress100%As of 2025-06-30
Completion2025-05-18Revised · Proposed 2023-08-19
Registered on2020-04-29
Cases6
Sections
| Property title & search report | |
|---|---|
| Disputes & cases | 6 cases |
| Contract & costs | 2 cost heads · 19 quarters |
| Technical report | |
| Site & area | 3 site details · 76 unit types |
| Construction & progress | 4 progress details · 19 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 134 documents · 12 source links |
Registration
Registration
| Promoter | M/S AGRAWAL CONSTRUCTION AND CONTRACTORS | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA290420001106 | |
| Registered on | 2020-04-29 | |
| Project type | Group Housing | |
| Status (as filed) | New | |
| Proposed completion | 2023-08-19 | |
| Revised completion | 2025-05-18 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| M-PRO-2026-03780 | CG RERA | Complaint | Disposed | 2026-09-30 |
| M-PRO-2025-02810 | CG RERA | Complaint | Disposed | 2026-02-16 |
| M-PRO-2024-02380 | CG RERA | Complaint | Disposed | 2024-08-12 |
| M-COM-2023-02046 | CG RERA | Complaint | Disposed | 2024-05-29 |
| M-PRO-2022-01849 | CG RERA | Complaint | Disposed | 2023-06-12 |
| M-PRO-2022-01848 | CG RERA | Complaint | Disposed | 2023-06-12 |
Complaints & cases
| Cases | 6 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,51,35,000 | |
|---|---|---|
| Construction | ₹11,04,08,000 |
Quarterly money flows
| 2020-Q2 | ₹7,700 |
| 2020-Q3 | ₹509.91 |
| 2020-Q4 | ₹17,90,199.74 |
| 2021-Q1 | ₹2,80,519 |
| 2021-Q2 | ₹39,019 |
| 2021-Q3 | ₹6,83,883 |
| 2021-Q4 | ₹24,913 |
| 2022-Q1 | ₹70 |
| 2022-Q2 | ₹17,766 |
| 2022-Q3 | ₹15,85,092 |
| 2022-Q4 | ₹1,06,223 |
| 2023-Q1 | ₹39,203 |
| 2023-Q2 | ₹876 |
| 2023-Q3 | ₹45 |
| 2023-Q4 | ₹447 |
| 2024-Q1 | ₹3 |
| 2024-Q4 | ₹2 |
| 2025-Q1 | ₹56,97,192 |
| 2025-Q2 | ₹1,05,893 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 76 | |
|---|---|---|
| Booked | 53 | |
| Booked as of | 2025-06-30 |
Unit types
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 62.55 | 1 | 0 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 3BHK | 81.41 | 1 | 1 |
| 3BHK | 85.68 | 1 | 1 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 62.55 | 1 | 0 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 81.41 | 1 | 1 |
| 3BHK | 85.68 | 1 | 1 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 62.55 | 1 | 0 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 3BHK | 85.68 | 1 | 1 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 62.55 | 1 | 0 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 3BHK | 81.41 | 1 | 1 |
| 3BHK | 85.68 | 1 | 1 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 62.55 | 1 | 0 |
| 2BHK | 62.44 | 1 | 0 |
| 2BHK | 61.59 | 1 | 1 |
| 3BHK | 81.41 | 1 | 1 |
| 3BHK | 85.68 | 1 | 0 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 62.55 | 1 | 0 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 3BHK | 81.41 | 1 | 1 |
| 3BHK | 85.68 | 1 | 0 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 62.55 | 1 | 0 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 3BHK | 81.41 | 1 | 1 |
| 3BHK | 85.68 | 1 | 0 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 2BHK | 62.55 | 1 | 0 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 62.44 | 1 | 1 |
| 2BHK | 61.59 | 1 | 1 |
| 3BHK | 81.41 | 1 | 1 |
| 3BHK | 85.68 | 1 | 0 |
| 2BHK | 62.44 | 1 | 0 |
| 2BHK | 61.59 | 1 | 1 |
| 3BHK | 78.6 | 1 | 1 |
| 3BHK | 78.25 | 1 | 0 |
| 3BHK | 78.25 | 1 | 1 |
| 4BHK | 96.22 | 1 | 0 |
| 2BHK | 62.44 | 1 | 0 |
| 2BHK | 62.44 | 1 | 0 |
| 2BHK | 62.44 | 1 | 0 |
| 2BHK | 62.44 | 1 | 0 |
| 2BHK | 62.44 | 1 | 0 |
| 2BHK | 62.44 | 1 | 0 |
| 2BHK | 62.44 | 1 | 0 |
| 3BHK | 81.41 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2025-06-30 | |
| Proposed completion | 2023-08-19 | |
| Revised completion | 2025-05-18 |
Quarterly progress
| 2020-Q2 | 1% |
| 2020-Q3 | 1% |
| 2020-Q4 | 1% |
| 2021-Q1 | 2% |
| 2021-Q2 | 3% |
| 2021-Q3 | 6% |
| 2021-Q4 | 7% |
| 2022-Q1 | 8% |
| 2022-Q2 | 14% |
| 2022-Q3 | 16% |
| 2022-Q4 | 18% |
| 2023-Q1 | 21% |
| 2023-Q2 | 24% |
| 2023-Q3 | 27% |
| 2023-Q4 | 30% |
| 2024-Q1 | 30% |
| 2024-Q4 | 41% |
| 2025-Q1 | 97% |
| 2025-Q2 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M/S AGRAWAL CONSTRUCTION AND CONTRACTORS | |
|---|---|---|
| Type | Other | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_completed.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTM3NQ==
- https://rera.cgstate.gov.in/cause_list.aspx
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2026-09-30 · Sign in to download
- Final order · 2026-02-16 · Sign in to download
- Final order · 2024-08-12 · Sign in to download
- Final order · 2024-05-29 · Sign in to download
- Final order · 2023-06-12 · Sign in to download
- Final order · 2023-06-12 · Sign in to download
- Interim order · 2024-01-05 · Sign in to download
- M-PRO-2026-03780 · Sign in to download
- M-PRO-2025-02810 · Sign in to download
- M-PRO-2024-02380 · Sign in to download
- M-COM-2023-02046 · Sign in to download
- M-PRO-2022-01849 · Sign in to download
- M-PRO-2022-01848 · Sign in to download