Overview
PANCHKULA ECO CITY
IDYLLIC RESORTS PVT LTD · Panchkula
Completion2020-12-12Proposed
Valid to2022-09-11
Approvals9
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 7 unit types |
| Construction & progress | 1 progress detail |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 13 documents · 4 source links |
Registration
Registration
| Promoter | IDYLLIC RESORTS PVT LTD | |
|---|---|---|
| District | Panchkula | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-PKL-65-2018 | |
| Valid to | 2022-09-11 | |
| Status (as filed) | Registered | |
| Proposed completion | 2020-12-12 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 46 of 2012 dated 12.05.2012 | Town & Country Planning Department | |
| Layout Plan | 2012-05-12 | ||
| Building Plan | 2012-05-12 | ||
| I. RENEWAL OF LICENSE | 2018-07-09 | ||
| II. ACCESS PERMISSION TO PRIVATE PROPERTIES ON NATIONAL HIGHWAYS. | 2018-02-21 | ||
| III. ULTIMATE LOAD & ELECTRIFICATION PLAN OF THE SECTOR | 2018-01-19 | ||
| IV. ISSUE OF CONSENT TO ESTABLISH FROM HARYANA POLLUTION BOARD. | 2013-11-05 | ||
| V. ZONING PLAN | 2013-08-06 | ||
| VI. LAY OUT PLAN OF THE SECTOR | 2012-05-12 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Status |
|---|---|---|
| RERA-PKL-2828-2022 | HRERA Panchkula | Disposed |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹24,00,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹59,64,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 0 |
|---|
Unit types
| 1 | 1,000 |
| 2 | 500 |
| 3 | 347 |
| 4 | 269 |
| 5 | 237 |
| 6 | |
| 7 | 50 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2020-12-12 |
|---|
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | IDYLLIC RESORTS PVT LTD | |
|---|---|---|
| Escrow bank | ALLAHABAD BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/SFJFUkEtUEtMLVBLTC02NS0yMDE4
- https://haryanarera.gov.in/view_project/project_preview_open/57
- https://nominatim.openstreetmap.org/search?q=sector+12%2C+Panchkula%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2018-10-15
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2018-10-15
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2018-10-15
- DEMARCATION PLAN · 2018-10-15
- ZONING PLAN · 2018-10-15
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2018-10-15
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2018-10-15
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2018-10-15 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2018-10-15 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2018-10-15 · Sign in to download
- RC Uploaded · 2023-03-01 · Sign in to download
- Completion certificate uploaded · 2023-06-08 · Sign in to download