Overview
PARAMPARA
C.G. BUILDCON PVT. LTD. · RAIPUR
Units86
Booked0 of 86As of 2026-06-30
Construction progress10%As of 2026-06-30
Completion2030-11-30Revised · Proposed 2030-07-31
Registered on2026-01-09
Approvals3
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 2 cost heads · 2 quarters |
| Technical report | |
| Site & area | 3 site details · 86 unit types |
| Construction & progress | 4 progress details · 2 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 26 documents · 9 source links |
Registration
Registration
| Promoter | C.G. BUILDCON PVT. LTD. | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA090126002025 | |
| Registered on | 2026-01-09 | |
| Project type | Residential Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2030-07-31 | |
| Revised completion | 2030-11-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| SM-PAP-2026-03431 | CG RERA | Complaint | Disposed | 2026-01-07 |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,83,34,000 | |
|---|---|---|
| Construction | ₹7,20,02,000 |
Quarterly money flows
| Quarter | Escrow balance |
|---|---|
| 2026-Q1 | ₹0 |
| 2026-Q2 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 86 | |
|---|---|---|
| Booked | 0 | |
| Booked as of | 2026-06-30 |
Unit types
| 1-1 | 1 | 0 |
| 2-2 | 1 | 0 |
| 3-3 | 1 | 0 |
| 4-4 | 1 | 0 |
| 5-5 | 1 | 0 |
| 6-6 | 1 | 0 |
| 7-7 | 1 | 0 |
| 8-8 | 1 | 0 |
| 9-9 | 1 | 0 |
| 10-10 | 1 | 0 |
| 11-11 | 1 | 0 |
| 12-12 | 1 | 0 |
| 13-13 | 1 | 0 |
| 14-14 | 1 | 0 |
| 15-15 | 1 | 0 |
| 16-16 | 1 | 0 |
| 17-17 | 1 | 0 |
| 18-18 | 1 | 0 |
| 19-19 | 1 | 0 |
| 20-20 | 1 | 0 |
| 21-21 | 1 | 0 |
| 22-22 | 1 | 0 |
| 23-23 | 1 | 0 |
| 24-24 | 1 | 0 |
| 25-25 | 1 | 0 |
| 26-26 | 1 | 0 |
| 27-27 | 1 | 0 |
| 28-28 | 1 | 0 |
| 29-29 | 1 | 0 |
| 30-30 | 1 | 0 |
| 31-31 | 1 | 0 |
| 32-32 | 1 | 0 |
| 33-33 | 1 | 0 |
| 34-34 | 1 | 0 |
| 35-35 | 1 | 0 |
| 36-36 | 1 | 0 |
| 37-37 | 1 | 0 |
| 38-38 | 1 | 0 |
| 39-39 | 1 | 0 |
| 40-40 | 1 | 0 |
| 41-41 | 1 | 0 |
| 42-42 | 1 | 0 |
| 43-43 | 1 | 0 |
| 44-44 | 1 | 0 |
| 45-45 | 1 | 0 |
| 46-46 | 1 | 0 |
| 47-47 | 1 | 0 |
| 48-48 | 1 | 0 |
| 49-49 | 1 | 0 |
| 50-50 | 1 | 0 |
| 51-51 | 1 | 0 |
| 52-52 | 1 | 0 |
| 53-53 | 1 | 0 |
| 54-54 | 1 | 0 |
| 55-55 | 1 | 0 |
| 56-56 | 1 | 0 |
| 57-57 | 1 | 0 |
| 58-58 | 1 | 0 |
| 59-59 | 1 | 0 |
| 60-60 | 1 | 0 |
| 61-61 | 1 | 0 |
| 62-62 | 1 | 0 |
| 63-63 | 1 | 0 |
| 64-64 | 1 | 0 |
| 65-65 | 1 | 0 |
| 66-66 | 1 | 0 |
| 67-67 | 1 | 0 |
| 68-68 | 1 | 0 |
| 69-69 | 1 | 0 |
| 70-70 | 1 | 0 |
| 71-71 | 1 | 0 |
| 72-72 | 1 | 0 |
| 73-73 | 1 | 0 |
| 74-74 | 1 | 0 |
| 75-75 | 1 | 0 |
| 76-76 | 1 | 0 |
| 77-77 | 1 | 0 |
| 78-78 | 1 | 0 |
| 79-79 | 1 | 0 |
| 80-80 | 1 | 0 |
| 81-81 | 1 | 0 |
| L-1-L-1 | 1 | 0 |
| L-2-L-2 | 1 | 0 |
| L-3-L-3 | 1 | 0 |
| L-4-L-4 | 1 | 0 |
| L-5-L-5 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 10% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2030-07-31 | |
| Revised completion | 2030-11-30 |
Quarterly progress
| Quarter | Progress |
|---|---|
| 2026-Q1 | 8% |
| 2026-Q2 | 10% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | C.G. BUILDCON PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 5 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MjQ3Mw==
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Development Permission from competent authorities
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- Development Cost Description · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- Final order · 2026-01-07 · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities
- SM-PAP-2026-03431 · Sign in to download