Overview
PARK SENTOSA
BPTP LIMITED · Faridabad
Units568
Booked252 of 568
Completion2020-07-31Revised · Proposed 2020-07-31
Registered on2017-10-13
Valid to2022-07-31
Approvals8
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Disputes & cases | 1 case · 2 registration details |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 4 site details · 2 unit types |
| Construction & progress | 3 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 5 documents · 5 source links |
Registration
Registration
| Promoter | BPTP LIMITED | |
|---|---|---|
| District | Faridabad | |
| Regulator | HRERA Panchkula | |
| Registration number | 296 OF 2018 DATED 13-10-2017 | |
| Registered on | 2017-10-13 | |
| Valid to | 2022-07-31 | |
| Status (as filed) | Lapsed Project | |
| Proposed completion | 2020-07-31 | |
| Revised completion | 2020-07-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | License No 267 of 2007 dated 03.12.2007 | Town & Country Planning Department | |
| Layout Plan | 2009-11-10 | ||
| Building Plan | 2009-11-10 | ||
| I. LICENSE NO 267 OF 2007 | 2007-12-03 | ||
| II. SERVICE PLAN ESTIMATE APPROVAL | 2011-09-06 | ||
| III. ZONING PLAN APPROVAL | 2008-08-18 | ||
| IV. ENVIRONMENTAL CLEARANCE APPROVAL | 2008-02-04 | ||
| V. ELECTRICAL LOAD APPROVAL | 2017-08-29 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Status |
|---|---|---|
| RERA-PKL-1892-2019 | HRERA Panchkula | Disposed |
Complaints & cases
| Cases | 1 |
|---|
Registration status
| Status | Lapsed Project | |
|---|---|---|
| Valid to | 2022-07-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,66,52,000 | |
|---|---|---|
| Construction | ₹1,54,46,52,000 | |
| Total | ₹2,31,21,83,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 30,715 | |
|---|---|---|
| FAR | 1.75 | |
| Units | 568 | |
| Booked | 252 |
Unit types
| Type | Units | Booked |
|---|---|---|
| APARTMENT/SHOPS/OTHER BUILDINGS Type APARTMENTS | 420 | 159 |
| APARTMENT/SHOPS/OTHER BUILDINGS Type EWS | 148 | 93 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2015-04-01 | |
|---|---|---|
| Proposed completion | 2020-07-31 | |
| Revised completion | 2020-07-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BPTP LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | PUNJAB NATIONAL BANK | |
| Other projects in this city pack | 16 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/assistancecontrol/print_quarterly_schedules/MQ==/NTkw/MjAxOQ==
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/Mjk2IG9mIDIwMTggZGF0ZWQgMTMtMTAtMjAxNw==
- https://haryanarera.gov.in/view_project/project_preview_open/684
- https://nominatim.openstreetmap.org/search?q=sector+77%2C+Faridabad%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2017-10-13
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-06-29
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-06-29
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-06-29 · Sign in to download
- ZONING PLAN · 2019-06-29