Overview
PARSVNATH CITY , SONEPAT(20.159 ACRES)
PARSVNATH DEVELOPERS LIMITED · Sonipat
Units321
Completion2021-06-30Revised · Proposed 2021-06-30
Registered on2017-10-24
Valid to2021-06-30
Approvals4
Cases2
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Disputes & cases | 2 cases · 2 registration details |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 3 unit types |
| Construction & progress | 3 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 8 documents · 3 source links |
Registration
Registration
| Promoter | PARSVNATH DEVELOPERS LIMITED | |
|---|---|---|
| District | Sonipat | |
| Regulator | HRERA Panchkula | |
| Registration number | 332 OF 2017 DATED 24.10.2017 | |
| Registered on | 2017-10-24 | |
| Valid to | 2021-06-30 | |
| Status (as filed) | Lapsed Project | |
| Proposed completion | 2021-06-30 | |
| Revised completion | 2021-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 915-945 of 2006(07-05-2019) | Town & Country Planning Department | |
| Layout Plan | 2006-05-01 | ||
| Building Plan | 2007-06-01 | ||
| I. SERVICE ESTIMATES PLAN | 2012-12-29 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Status |
|---|---|---|
| RERA-PKL-1988-2019 | HRERA Panchkula | |
| RERA-PKL-1990-2022 | HRERA Panchkula | Disposed |
Complaints & cases
| Cases | 2 |
|---|
Registration status
| Status | Lapsed Project | |
|---|---|---|
| Valid to | 2021-06-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹15,10,00,000 | |
|---|---|---|
| Construction | ₹92,95,00,000 | |
| Total | ₹1,30,03,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 321 |
|---|
Unit types
| Type | Units |
|---|---|
| 1 | 15 |
| 2 | 162 |
| 3 | 144 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2006-05-01 | |
|---|---|---|
| Proposed completion | 2021-06-30 | |
| Revised completion | 2021-06-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | PARSVNATH DEVELOPERS LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | SYNDICATE BANK | |
| Other projects in this city pack | 11 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/MzMyIG9mIDIwMTcgZGF0ZWQgMjQuMTAuMjAxNw==
- https://haryanarera.gov.in/view_project/project_preview_open/357
- Registration Certificate · 2017-10-24
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2019-11-01
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-11-01 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-11-01
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-11-01
- DEMARCATION PLAN · 2019-11-01
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2019-11-01
- ZONING PLAN · 2019-11-01