Overview
PARSVNATH PALIWAL CITY PANIPAT
PARSVNATH DEVELOPERS LIMITED · Panipat
Units428
Completion2020-03-31Revised · Proposed 2020-03-31
Valid to2020-03-31
Approvals5
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Disputes & cases | 1 case · 2 registration details |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 3 unit types |
| Construction & progress | 3 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 10 documents · 3 source links |
Registration
Registration
| Promoter | PARSVNATH DEVELOPERS LIMITED | |
|---|---|---|
| District | Panipat | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-PNP-120-2019 | |
| Valid to | 2020-03-31 | |
| Status (as filed) | Lapsed Project | |
| Proposed completion | 2020-03-31 | |
| Revised completion | 2020-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 163-171 of 2007(30.03.2015) | Town & Country Planning Department | |
| Layout Plan | 2015-04-24 | ||
| Building Plan | 2009-07-02 | ||
| I. CONSENT TO ESTABLISH | 2008-01-22 | ||
| II. ENVIRONMENTAL CLEARANCE | 2009-05-04 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Status |
|---|---|---|
| RERA-PKL-695-2020 | HRERA Panchkula | Disposed |
Complaints & cases
| Cases | 1 |
|---|
Registration status
| Status | Lapsed Project | |
|---|---|---|
| Valid to | 2020-03-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹36,20,00,000 | |
|---|---|---|
| Construction | ₹9,05,00,000 | |
| Total | ₹1,53,91,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 428 |
|---|
Unit types
| Type | Units |
|---|---|
| 1 | 113 |
| 2 | 134 |
| 3 | 181 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2007-05-01 | |
|---|---|---|
| Proposed completion | 2020-03-31 | |
| Revised completion | 2020-03-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | PARSVNATH DEVELOPERS LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | SYNDICATE BANK | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/SFJFUkEtUEtMLVBOUC0xMjAtMjAxOQ==
- https://haryanarera.gov.in/view_project/project_preview_open/69
- Registration Certificate
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-03-02
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2019-03-02
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2019-03-02 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-03-02
- DEMARCATION PLAN · 2019-03-02
- ZONING PLAN · 2019-03-02
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-03-02
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2019-03-02
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-03-02 · Sign in to download