Overview
Patiala Heights
OM Constructions · Patiala
Units169
Completion2020-12-31Proposed
Valid to2022-12-31
Approvals8
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 3 unit types |
| Construction & progress | 2 progress details · 11 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 21 documents · 21 source links |
Registration
Registration
| Promoter | OM Constructions | |
|---|---|---|
| District | Patiala | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-PTL63-PR0165 | |
| Valid to | 2022-12-31 | |
| Project type | (1) Commercial (Building/Tower Development) (2) Residential (Building/Tower Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2020-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| Electric Substation NOC | 2015-02-26 | |
| License as Promoter from competent Authority | 2014-11-07 | |
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | Permissions (Received) | 2015-12-14 |
| Other Document (FOREST NOC) | 2015-02-20 | |
| Pollution Clearance from Punjab Pollution Control Board | 2016-01-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹64,42,14,750 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 8,092 | |
|---|---|---|
| Towers | 3 | |
| Maximum floors | 66 | |
| Units | 169 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| 3 BHK | 122.361 | 51 | BLOCK A |
| 3 BHK | 126.384 | 52 | BLOCK B |
| 3 BHK | 131.703 | 66 | BLOCK C |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2015-04-01 | |
|---|---|---|
| Proposed completion | 2020-12-31 |
Quarterly progress
| 2019-Q4 | 2020-08-21 |
| 2020-Q1 | 2020-08-22 |
| 2020-Q3 | 2022-09-05 |
| 2020-Q4 | 2022-09-05 |
| 2021-Q1 | 2022-09-05 |
| 2021-Q2 | 2022-09-05 |
| 2021-Q3 | 2022-09-05 |
| 2021-Q4 | 2022-09-05 |
| 2022-Q1 | 2022-09-05 |
| 2022-Q2 | 2022-09-05 |
| 2020-Q2 | 2022-09-15 |
Extensions
| Valid to |
|---|
| 2022-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | OM Constructions | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Punjab National Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10315&inPromoter_ID=1281&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2015-02-26
- License as Promoter from competent Authority · 2014-11-07
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2015-12-14
- Other Document (FOREST NOC) · 2015-02-20
- Pollution Clearance from Punjab Pollution Control Board · 2016-01-29
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- Electric Substation NOC · 2015-02-26
- License as Promoter from competent Authority · 2014-11-07
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2015-12-14
- Other Document (FOREST NOC) · 2015-02-20
- Pollution Clearance from Punjab Pollution Control Board · 2016-01-29
- 2019-Q4 · 2020-08-21
- 2020-Q1 · 2020-08-22
- 2020-Q3 · 2022-09-05
- 2020-Q4 · 2022-09-05
- 2021-Q1 · 2022-09-05
- 2021-Q2 · 2022-09-05
- 2021-Q3 · 2022-09-05
- 2021-Q4 · 2022-09-05
- 2022-Q1 · 2022-09-05
- 2022-Q2 · 2022-09-05
- 2020-Q2 · 2022-09-15