Overview
Pawan Enclave
PVS Builders and Colonizers Pvt. Ltd. · Sangrur
Units35
Completion2027-03-31Proposed
Valid to2027-03-31
Approvals6
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 1 unit type |
| Construction & progress | 2 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 20 documents · 17 source links |
Registration
Registration
| Promoter | PVS Builders and Colonizers Pvt. Ltd. | |
|---|---|---|
| District | Sangrur | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SGR73-PC0253 | |
| Valid to | 2027-03-31 | |
| Project type | (1) Commercial (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2027-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | |
| Electric Substation NOC | 2024-02-21 |
| Environment Clearance certificate/ NOC | 2024-02-09 |
| License as Promoter from competent Authority | 2022-09-14 |
| License to develop colony or society from Competent Authority | |
| NOC from NHAI/ PWD | 2023-09-01 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹2,36,41,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 7,511.97 | |
|---|---|---|
| Units | 35 |
Unit types
| Type | Carpet (m²) | Units |
|---|---|---|
| Plotted | 3,149.91 | 35 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-02-01 | |
|---|---|---|
| Proposed completion | 2027-03-31 |
Quarterly progress
| 2024-Q3 | 2026-01-26 |
| 2024-Q4 | 2026-01-26 |
| 2025-Q1 | 2026-01-26 |
| 2025-Q2 | 2026-01-26 |
| 2025-Q3 | 2026-01-26 |
| 2025-Q4 | 2026-01-26 |
| 2026-Q1 | 2026-04-13 |
| 2026-Q2 | 2026-07-13 |
| 2026-Q3 | 2026-10-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | PVS Builders and Colonizers Pvt. Ltd. | |
|---|---|---|
| Type | Company | |
| Escrow bank | Union Bank of India | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11914&inPromoter_ID=2808&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2024-02-21
- Environment Clearance certificate/ NOC · 2024-02-09
- License as Promoter from competent Authority · 2022-09-14
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2023-09-01
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- Electric Substation NOC · 2024-02-21
- Environment Clearance certificate/ NOC · 2024-02-09
- License as Promoter from competent Authority · 2022-09-14
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2023-09-01
- 2024-Q3 · 2026-01-26
- 2024-Q4 · 2026-01-26
- 2025-Q1 · 2026-01-26
- 2025-Q2 · 2026-01-26
- 2025-Q3 · 2026-01-26
- 2025-Q4 · 2026-01-26
- 2026-Q1 · 2026-04-13
- 2026-Q2 · 2026-07-13
- 2026-Q3 · 2026-10-15