Overview
PHASE-2 DEVELOPMENT OF MEGA RESIDENTIAL PROJECT AT MULLANPUR
Omaxe New Chandigarh Developers Private Ltd. · Sahibzada Ajit Singh Nagar (Mohali)
Units450
Completion2022-12-31Proposed
Valid to2019-01-31
Approvals4
Cases6
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Disputes & cases | 6 cases |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 37 unit types |
| Construction & progress | 2 progress details · 27 quarters |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 29 documents · 34 source links |
Registration
Registration
| Promoter | Omaxe New Chandigarh Developers Private Ltd. | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS80-PR0032 | |
| Valid to | 2019-01-31 | |
| Project type | (1) Residential (Building/Tower Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2022-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Electric Substation NOC | Clearances (Received) | 2015-04-20 |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2015-03-25 |
| License as Promoter from competent Authority | 2013-11-19 | |
| Pollution Clearance from Punjab Pollution Control Board | Clearances (Received) | 2018-01-17 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| CC/738/2017 | SCDRC,CHANDIGARH |
| CC No.826 of 2015 | DCDRF,CHANDIGARH |
| CC/608/2017 | SCDRC,CHANDIGARH |
| CC/732/2017 | SCDRC,CHANDIGARH |
| First Appeal No.1208 of 2016 | NCDRC,DELHI |
| FA/2374/2017 | NCDRC,NEW DELHI |
Complaints & cases
| Cases | 6 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹1,84,04,71,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 37,463.78 | |
|---|---|---|
| Towers | 36 | |
| Maximum floors | 4 | |
| Units | 450 |
Unit types
| 3 BHK | 94.95 | 54 | TYPE A |
| 3 BHK | 101.73 | 69 | TYPE B |
| 3 BHK | 106.32 | 132 | TYPE C |
| 3 BHK | 107.82 | 3 | TYPE D |
| 4 BHK | 107.82 | 6 | TYPE D |
| 3 BHK | 108.43 | 6 | TYPE E |
| 3 BHK | 108.64 | 3 | TYPE F |
| 4 BHK | 152.08 | 3 | TYPE G |
| 4 BHK | 152.11 | 3 | TYPE H |
| 4 BHK | 153.05 | 81 | TYPE I |
| Villa | 351.41 | 1 | VILLA 9 |
| Villa | 396.41 | 1 | VILLA 312 |
| Villa | 213.4 | 1 | VILLA 445 |
| Villa | 264.7 | 1 | VILLA 266N |
| VILLA | 267.79 | 1 | VILLA 357K |
| Villa | 219.33 | 1 | VILLA 374I |
| 3 BHK | 123.75 | 4 | 520 K |
| 3 BHK | 123.75 | 4 | 523 K |
| 4 BHK+ SERVANT | 188.22 | 4 | 523 L |
| 4 BHK+SERVANT | 188.22 | 4 | 523 AI |
| 3 BHK+SERVANT | 135.54 | 4 | 0504 |
| 3 BHK | 115.01 | 4 | 504A |
| 3 BHK | 137.68 | 4 | 553A |
| 3 BHK | 134.06 | 4 | 553 B |
| 3 BHK | 115.01 | 4 | 0554 |
| 3 BHK | 116.69 | 4 | 554 A |
| 3 BHK | 116.69 | 4 | 554 B |
| 3 BHK | 116.69 | 4 | 554 C |
| 3 BHK | 116.69 | 4 | 554 D |
| 3 BHK | 116.69 | 4 | 554 E |
| 3 BHK | 135.54 | 4 | 554 F |
| 3 BHK | 81.85 | 4 | 0785 |
| 3 BHK | 83.05 | 4 | 785 A |
| 3 BHK | 83.05 | 4 | 785 B |
| 3 BHK | 83.05 | 4 | 785C |
| 3 BHK | 83.05 | 4 | 785 D |
| 3 BHK | 81.85 | 4 | 785 E |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2012-02-01 | |
|---|---|---|
| Proposed completion | 2022-12-31 |
Quarterly progress
| 2021-Q3 | 2021-12-21 |
| 2021-Q4 | 2022-02-18 |
| 2022-Q1 | 2022-04-25 |
| 2022-Q2 | 2022-07-26 |
| 2022-Q3 | 2022-10-28 |
| 2021-Q1 | 2022-11-05 |
| 2020-Q1 | 2022-11-05 |
| 2020-Q2 | 2022-11-05 |
| 2020-Q3 | 2022-11-05 |
| 2020-Q4 | 2022-11-05 |
| 2021-Q2 | 2022-11-05 |
| 2022-Q4 | 2023-01-16 |
| 2023-Q1 | 2023-05-04 |
| 2023-Q2 | 2023-07-20 |
| 2023-Q3 | 2023-10-17 |
| 2023-Q4 | 2024-01-16 |
| 2024-Q1 | 2024-05-02 |
| 2024-Q2 | 2024-07-14 |
| 2024-Q3 | 2024-10-10 |
| 2024-Q4 | 2025-01-08 |
| 2025-Q1 | 2025-04-12 |
| 2025-Q2 | 2025-07-14 |
| 2025-Q3 | 2025-10-10 |
| 2025-Q4 | 2026-01-12 |
| 2026-Q1 | 2026-04-13 |
| 2026-Q2 | 2026-07-14 |
| 2026-Q3 | 2026-10-12 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Omaxe New Chandigarh Developers Private Ltd. | |
|---|---|---|
| Type | Company | |
| Escrow bank | Axis Bank Limited | |
| Other projects in this city pack | 37 |
Professional firms
| Role | Firm |
|---|---|
| Agent | AMRIT ASSOCIATES |
| Agent | FAMILY NEST REAL ESTATES PVT LTD |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10150&inPromoter_ID=1072&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- Amendments or revisions in sanctioned Layout/ Sanction / Building Plan · 2017-01-12
- Borewell Registration certificate from Central Ground Water Authority · 2014-02-04
- Commencement Certificate (Mega Project Category) · Sign in to download
- Electric Substation NOC · 2015-04-20
- Environment Clearance certificate/ NOC · 2015-03-25
- License as Promoter from competent Authority · 2013-11-19
- Other Document (letter of intent) · 2009-09-23 · Sign in to download
- Other Document (REVISE SERVICE PLAN) · 2017-09-27
- Other Document (REVISED ZONING PLAN) · 2017-04-18
- Pollution Clearance from Punjab Pollution Control Board · 2018-01-17
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Advertisement and Brochure/ Prospectus · Sign in to download
- Electric Substation NOC · 2015-04-20
- Environment Clearance certificate/ NOC · 2015-03-25
- License as Promoter from competent Authority · 2013-11-19
- Pollution Clearance from Punjab Pollution Control Board · 2018-01-17
- 2021-Q3 · 2021-12-21
- 2021-Q4 · 2022-02-18
- 2022-Q1 · 2022-04-25
- 2022-Q2 · 2022-07-26
- 2022-Q3 · 2022-10-28
- 2021-Q1 · 2022-11-05
- 2020-Q1 · 2022-11-05
- 2020-Q2 · 2022-11-05
- 2020-Q3 · 2022-11-05
- 2020-Q4 · 2022-11-05
- 2021-Q2 · 2022-11-05
- 2022-Q4 · 2023-01-16
- 2023-Q1 · 2023-05-04
- 2023-Q2 · 2023-07-20
- 2023-Q3 · 2023-10-17
- 2023-Q4 · 2024-01-16
- 2024-Q1 · 2024-05-02
- 2024-Q2 · 2024-07-14
- 2024-Q3 · 2024-10-10
- 2024-Q4 · 2025-01-08
- 2025-Q1 · 2025-04-12
- 2025-Q2 · 2025-07-14
- 2025-Q3 · 2025-10-10
- 2025-Q4 · 2026-01-12
- 2026-Q1 · 2026-04-13
- 2026-Q2 · 2026-07-14
- 2026-Q3 · 2026-10-12