Overview
PICASSO CENTRE
ERA RESORTS PVT LTD · Gurugram
Completion2019-12-31Revised · Proposed 2019-12-31
Registered on2018-09-06
Valid to2020-12-30
Approvals9
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Disputes & cases | 2 registration details |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 10 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 51 documents · 2 source links |
Registration
Registration
| Promoter | ERA RESORTS PVT LTD | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/282/2018/14 DATED 06.09.2018 | |
| Registered on | 2018-09-06 | |
| Valid to | 2020-12-30 | |
| Status (as filed) | Lapsed Project | |
| Proposed completion | 2019-12-31 | |
| Revised completion | 2019-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 278 of 2007 (17-12-2007) | Town & Country Planning Department | |
| Layout Plan | 2012-12-27 | ||
| Building Plan | 2012-12-27 | ||
| I. ZONNING PLAN | 2012-05-30 | ||
| II. BUILDING PLAN | 2012-12-27 | ||
| III. ARAVALI CLEARANCE THROUGH DC | 2013-09-02 | ||
| IV. CONSENT TO ESTABLISHMENT | 2018-08-27 | ||
| V. CLEARANCE FROM MINING DEPARTMENT | 2013-06-27 | ||
| VI. SERVICES ESTIMATE | 2014-02-17 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Registration status
| Status | Lapsed Project | |
|---|---|---|
| Valid to | 2020-12-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,05,00,000 | |
|---|---|---|
| Construction | ₹44,69,60,999.99999994 | |
| Total | ₹84,57,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 9,558.67 | |
|---|---|---|
| FAR | 150 |
Unit types
| Type |
|---|
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| 7 |
| 8 |
| 9 |
| 10 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2019-12-31 | |
|---|---|---|
| Revised completion | 2019-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ERA RESORTS PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/947
- Registration Certificate · 2018-09-06
- ZONING PLAN · 2019-11-28
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-11-28
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2019-11-28 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-11-28
- NOC FROM ENVIRONMENT CTE STATE POLLUTION NORMS · 2019-11-28
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2019-11-28 · Sign in to download
- CTE CERTIFICATE · 2019-11-28 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-11-23
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2019-11-28
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2019-11-28 · Sign in to download
- MINING APPROVAL · 2019-11-28
- LOI · 2020-02-28 · Sign in to download
- SITE PLAN FOR SEWERAGE LAYOUT · 2020-02-28
- SEVENTH FLOOR PLAN · 2020-02-28
- SITE PLAN · 2020-02-28
- SITE PLAN FOR DRAINAGE LAYOUT · 2020-02-28
- ELEVATION C · 2020-02-28 · Sign in to download
- GROUND FLOOR PLAN · 2020-02-28
- ACKNOWLEDGE FOR APPLY OF FIRE APPLICATION · 2020-02-28 · Sign in to download
- NON ENCUMBRANCE CERTIFICATE · 2020-02-28 · Sign in to download
- SECOND BASEMENT PLAN · 2020-02-28
- LICENSE RENEWAL · 2020-02-28
- SECOND FLOOR PLAN · 2020-02-28
- DECLARATION FOR SERVICE ESTIMATE · 2020-02-28 · Sign in to download
- SITE PLAN · 2020-02-28
- ZONAL PLAN PICASSO · 2020-02-28
- SECTION XX · 2020-02-28 · Sign in to download
- SIXTH FLOOR PLAN · 2020-02-28
- SITE PLAN FOR ROAD LAYOUT · 2020-02-28
- ELEVATION D · 2020-02-28 · Sign in to download
- ACKNOWLEDGE FOR APPLY OF SERVICE PLAN · 2020-02-28
- BOR FOR BANK OPERATION · 2020-02-28 · Sign in to download
- AREA DETAIL PLAN · 2020-02-28
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2020-02-28 · Sign in to download
- DTCP LICENSE ORIGINAL ALONG WITH LAND SCHEDULE · 2020-02-28
- DECLARATION FOR FIRE SCHEME · 2020-02-28 · Sign in to download
- FORM LC-IV · 2020-02-28 · Sign in to download
- MINING APPROVAL · 2020-02-28
- LETTER BUILDING PLAN · 2020-02-28
- NOC ARVALI INCLUDE FOREST · 2020-02-28
- EIGHTH FLOOR PLAN · 2020-02-28
- TOD APPROVAL · 2020-02-28
- ZONING APPROVAL LETTER · 2020-02-28
- SITE PLAN FOR WATER SUPPLY LAYOUT · 2020-02-28
- ELEVATION A · 2020-02-28 · Sign in to download
- ELEVATION B · 2020-02-28 · Sign in to download
- FIFTH SERVICE FLOOR PLAN · 2020-02-28
- FIRST BASEMENT PLAN · 2020-02-28
- FIRST FLOOR PLAN · 2020-02-28
- EXTENSION NO. HARERA/GGM/REP/RC/14/2018/EXT/2013/2019 DATED-17.08.2020 · 2020-08-19 · Sign in to download