Overview
PLATINUM RANJIT MINAKSHI RESIDENCY
M S DEVELOPERS · Patna
Units20
Completion2021-08-30Proposed
Registered on2022-01-20
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 6 unit types |
| Construction & progress | 2 progress details · 12 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 21 documents · 17 source links |
Registration
Registration
| Promoter | M S DEVELOPERS | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00635-1/498/R-190/2018 | |
| Registered on | 2022-01-20 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Completed | |
| Proposed completion | 2021-08-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc. |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,04,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,054.65 | |
|---|---|---|
| Built-up (m²) | 1,502.32 | |
| FAR | 1.42 | |
| Towers | 2 | |
| Units | 20 |
Unit types
| 1 BHK | 1 | BLOCK A |
| 2 BHK | 5 | BLOCK A |
| 3 BHK | 4 | BLOCK A |
| 1 BHK | 1 | BLOCK B |
| 2 BHK | 5 | BLOCK B |
| 3 BHK | 4 | BLOCK B |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-07-01 | |
|---|---|---|
| Proposed completion | 2021-08-30 |
Quarterly progress
| 2021-Q3 | 2022-01-12 |
| 2021-Q2 | 2022-01-12 |
| 2021-Q1 | 2021-12-29 |
| 2020-Q4 | 2021-02-11 |
| 2020-Q3 | 2021-02-11 |
| 2020-Q2 | 2021-02-11 |
| 2020-Q1 | 2020-11-18 |
| 2019-Q4 | 2020-06-04 |
| 2019-Q3 | 2020-06-04 |
| 2019-Q2 | 2020-06-04 |
| 2019-Q1 | 2019-12-31 |
| 2018-Q4 | 2019-05-01 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M S DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Kotak Mahindra | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP237201800635-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP237201800635-1
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- Approved Layout Plan
- Area Development Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q2-Jul to Sep / 2021-2022 · 2022-01-12
- Q1-Apr to Jun / 2021-2022 · 2022-01-12
- Q4-Jan to Mar / 2020-2021 · 2021-12-29
- Q3-Oct to Dec / 2020-2021 · 2021-02-11
- Q2-Jul to Sep / 2020-2021 · 2021-02-11
- Q1-Apr to Jun / 2020-2021 · 2021-02-11
- Q4-Jan to Mar / 2019-2020 · 2020-11-18
- Q3-Oct to Dec / 2019-2020 · 2020-06-04
- Q2-Jul to Sep / 2019-2020 · 2020-06-04
- Q1-Apr to Jun / 2019-2020 · 2020-06-04
- Q4-Jan to Mar / 2018-2019 · 2019-12-31
- Q3-Oct to Dec / 2018-2019 · 2019-05-01
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- 2021-Q3 · 2022-01-12
- 2021-Q2 · 2022-01-12
- 2021-Q1 · 2021-12-29
- 2020-Q4 · 2021-02-11
- 2020-Q3 · 2021-02-11
- 2020-Q2 · 2021-02-11
- 2020-Q1 · 2020-11-18
- 2019-Q4 · 2020-06-04
- 2019-Q3 · 2020-06-04
- 2019-Q2 · 2020-06-04
- 2019-Q1 · 2019-12-31
- 2018-Q4 · 2019-05-01