DOSLChhattisgarh Workspace

Overview

PMAY AT CHANTIDIH (319 DUS) BILASPUR

E.E.MUNICIPAL CORPORATION BILASPUR (C.G.) · BILASPUR
Construction progress32%As of 2024-06-30
Completion2025-06-19Revised · Proposed 2023-07-18
Registered on2022-03-25
Approvals3
Cases1

Sections

Property title & search report
Approvals3 approvals
Disputes & cases1 case
Contract & costs2 cost heads · 10 quarters
Technical report
Site & area321 unit types
Construction & progress4 progress details · 10 quarters
Developer & finance
Developer4 developer details · 2 professional firms
The evidence
Sources58 documents · 9 source links

Registration

Registration

PromoterE.E.MUNICIPAL CORPORATION BILASPUR (C.G.)
DistrictBILASPUR
RegulatorCG RERA
Registration numberPCGRERA250322001360
Registered on2022-03-25
Project typeGroup Housing
Status (as filed)Ongoing
Proposed completion2023-07-18
Revised completion2025-06-19