DOSLChhattisgarh Workspace

Overview

PMAY FOR 338(1875) DUS AT KHAMARIYA BHILAI DIST.-DURG

MUNICIPAL CORPORATION BHILAI · DURG
Units322
Booked0 of 322As of 2026-06-30
Construction progress95%As of 2026-06-30
Completion2027-07-30Revised · Proposed 2027-03-30
Registered on2022-04-08
Approvals3

Sections

Property title & search report
Approvals3 approvals
Contract & costs2 cost heads · 16 quarters
Technical report
Site & area3 site details · 322 unit types
Construction & progress4 progress details · 16 quarters
Developer & finance
Developer3 developer details · 2 professional firms
The evidence
Sources83 documents · 6 source links

Registration

Registration

PromoterMUNICIPAL CORPORATION BHILAI
DistrictDURG
RegulatorCG RERA
Registration numberPCGRERA080422001383
Registered on2022-04-08
Project typeGroup Housing
Status (as filed)Ongoing
Proposed completion2027-03-30
Revised completion2027-07-30