DOSLChhattisgarh Workspace

Overview

PMAY OF 696 DUS AT BIRGAON ,RAIPUR

COMMISSIONER BIRGAON MUNICIPAL CORPORATION · RAIPUR
Units696
Booked0 of 696As of 2024-06-30
Construction progress100%As of 2024-06-30
Completion2027-12-15Proposed
Registered on2022-12-22
Approvals5

Sections

Property title & search report
Approvals5 approvals
Contract & costs2 cost heads · 7 quarters
Technical report
Site & area3 site details · 697 unit types
Construction & progress3 progress details · 7 quarters
Developer & finance
Developer4 developer details · 2 professional firms
The evidence
Sources51 documents · 8 source links

Registration

Registration

PromoterCOMMISSIONER BIRGAON MUNICIPAL CORPORATION
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA221222001571
Registered on2022-12-22
Project typeGroup Housing
Status (as filed)New
Proposed completion2027-12-15