Overview
POWER GREEN CITY
M/S SARVMANGLA CONSTRUCTIONS · BILASPUR
Units53
Booked42 of 53As of 2025-03-31
Construction progress73%As of 2025-03-31
Completion2018-11-30Proposed
Registered on2018-06-23
Approvals3
Cases3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Disputes & cases | 3 cases |
| Contract & costs | 2 cost heads · 27 quarters |
| Technical report | |
| Site & area | 3 site details · 53 unit types |
| Construction & progress | 3 progress details · 27 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 129 documents · 11 source links |
Registration
Registration
| Promoter | M/S SARVMANGLA CONSTRUCTIONS | |
|---|---|---|
| District | BILASPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA230618000308 | |
| Registered on | 2018-06-23 | |
| Project type | Plotted Development | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2018-11-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| M-COM-2025-02772 | CG RERA | Complaint | Disposed | 2026-09-30 |
| SM-EXP-2024-02257 | CG RERA | Complaint | Disposed | 2024-09-23 |
| M-COM-2019-00397 | CG RERA | Complaint | Disposed | 2019-05-20 |
Complaints & cases
| Cases | 3 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹39,88,000 | |
|---|---|---|
| Construction | ₹4,28,00,000 |
Quarterly money flows
| 2018-Q3 | ₹0 |
| 2018-Q4 | ₹0 |
| 2019-Q1 | ₹0 |
| 2019-Q2 | ₹0 |
| 2019-Q3 | ₹0 |
| 2019-Q4 | ₹0 |
| 2020-Q1 | ₹0 |
| 2020-Q2 | ₹0 |
| 2020-Q3 | ₹0 |
| 2020-Q4 | ₹0 |
| 2021-Q1 | ₹0 |
| 2021-Q2 | ₹0 |
| 2021-Q3 | ₹0 |
| 2021-Q4 | ₹25,053 |
| 2022-Q1 | ₹0 |
| 2022-Q2 | ₹1,95,915.94 |
| 2022-Q3 | ₹675.84 |
| 2022-Q4 | ₹3,80,646.34 |
| 2023-Q1 | ₹3,80,646.34 |
| 2023-Q2 | ₹3,80,646.34 |
| 2023-Q3 | ₹3,80,646.34 |
| 2023-Q4 | ₹3,80,646.34 |
| 2024-Q1 | ₹3,80,646.34 |
| 2024-Q2 | ₹4,558.87 |
| 2024-Q3 | ₹4,556.51 |
| 2024-Q4 | ₹4,556.51 |
| 2025-Q1 | ₹2,993.01 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 53 | |
|---|---|---|
| Booked | 42 | |
| Booked as of | 2025-03-31 |
Unit types
| PLOT-8 | 1 | 0 |
| PLOT-14 | 1 | 0 |
| PLOT-15 | 1 | 0 |
| PLOT-20 | 1 | 1 |
| PLOT-31 | 1 | 0 |
| PLOT-32 | 1 | 0 |
| PLOT-33 | 1 | 0 |
| PLOT-34 | 1 | 0 |
| PLOT-35 | 1 | 1 |
| PLOT-36 | 1 | 0 |
| PLOT-37 | 1 | 1 |
| PLOT-38 | 1 | 0 |
| PLOT-39 | 1 | 0 |
| PLOT-45 | 1 | 0 |
| PLOT-53 | 1 | 1 |
| PLOT-40 | 1 | 1 |
| PLOT-27 | 1 | 1 |
| PLOT-25 | 1 | 1 |
| PLOT-30 | 1 | 1 |
| PLOT-50 | 1 | 1 |
| PLOT-49 | 1 | 1 |
| PLOT-51 | 1 | 1 |
| PLOT-52 | 1 | 1 |
| PLOT-22 | 1 | 1 |
| PLOT-18 | 1 | 1 |
| PLOT-10 | 1 | 1 |
| PLOT-12 | 1 | 1 |
| PLOT-47 | 1 | 1 |
| PLOT-13 | 1 | 1 |
| PLOT-16 | 1 | 1 |
| PLOT-28 | 1 | 1 |
| PLOT-44 | 1 | 1 |
| PLOT-48 | 1 | 1 |
| PLOT-43 | 1 | 1 |
| PLOT-5 | 1 | 1 |
| PLOT-6 | 1 | 1 |
| PLOT-46 | 1 | 1 |
| PLOT-41 | 1 | 1 |
| PLOT-29 | 1 | 1 |
| PLOT-2 | 1 | 1 |
| PLOT-42 | 1 | 1 |
| PLOT-4 | 1 | 1 |
| PLOT-7 | 1 | 1 |
| PLOT-9 | 1 | 1 |
| PLOT-11 | 1 | 1 |
| PLOT-17 | 1 | 1 |
| PLOT-19 | 1 | 1 |
| PLOT-1 | 1 | 1 |
| PLOT-3 | 1 | 1 |
| PLOT-23 | 1 | 1 |
| PLOT-24 | 1 | 1 |
| PLOT-26 | 1 | 1 |
| PLOT-21 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 73% | |
|---|---|---|
| As of | 2025-03-31 | |
| Proposed completion | 2018-11-30 |
Quarterly progress
| 2018-Q3 | 60% |
| 2018-Q4 | 60% |
| 2019-Q1 | 60% |
| 2019-Q2 | 60% |
| 2019-Q3 | 60% |
| 2019-Q4 | 60% |
| 2020-Q1 | 60% |
| 2020-Q2 | 60% |
| 2020-Q3 | 60% |
| 2020-Q4 | 60% |
| 2021-Q1 | 60% |
| 2021-Q2 | 60% |
| 2021-Q3 | 60% |
| 2021-Q4 | 61% |
| 2022-Q1 | 63% |
| 2022-Q2 | 66% |
| 2022-Q3 | 70% |
| 2022-Q4 | 70% |
| 2023-Q1 | 70% |
| 2023-Q2 | 70% |
| 2023-Q3 | 70% |
| 2023-Q4 | 70% |
| 2024-Q1 | 70% |
| 2024-Q2 | 73% |
| 2024-Q3 | 73% |
| 2024-Q4 | 73% |
| 2025-Q1 | 73% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M/S SARVMANGLA CONSTRUCTIONS | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=Mzk1
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2026-09-30 · Sign in to download
- Final order · 2024-09-23 · Sign in to download
- Final order · 2019-05-20
- Interim order · 2025-07-21 · Sign in to download
- Interim order · 2024-04-24 · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities
- M-COM-2025-02772 · Sign in to download
- SM-EXP-2024-02257 · Sign in to download