Overview
PRABHU VIHAR
RAMPHOOL CHOUDHARY · Jaipur
Units138
Booked40 of 138As of 2023-06-30
Completion2025-02-15Revised · Proposed 2022-02-28
Registered on2022-03-18
Valid to2025-02-15
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 49 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 60 documents · 6 source links |
Registration
Registration
| Promoter | RAMPHOOL CHOUDHARY | |
|---|---|---|
| District | Jaipur | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2022/1901 | |
| Registered on | 2022-03-18 | |
| Valid to | 2025-02-15 | |
| Project type | Plotted | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2022-02-28 | |
| Revised completion | 2025-02-15 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹25,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹2,26,68,148 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2023-Q2 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 19,500 | |
|---|---|---|
| Built-up (m²) | 11,243.06 | |
| Towers | 138 | |
| Units | 138 | |
| Booked | 40 | |
| Booked as of | 2023-06-30 |
Unit types
| Plot No. 9 | 1 | 0 |
| Plot No. 88, 89, 90, 91, 92, 93, 94, 95, 96, 97, 98, 99, 100, 101, 102, 103, 104, 105, 106, 107, 108 | 21 | 0 |
| Plot No. 11, 12, 13, 14, 15, 16, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 48, 49, 50, 51, 52, 53 | 32 | 0 |
| Plot No. 8 | 1 | 0 |
| Plot No. 7 | 1 | 0 |
| Plot No. 17, 47 | 2 | 0 |
| Plot No. 20, 44 | 2 | 0 |
| Plot No. 6 | 1 | 0 |
| Plot No. 65, 76 | 2 | 0 |
| Plot No. 66, 67, 68, 73, 74, 75 | 6 | 0 |
| Plot No. 70 | 1 | 0 |
| Plot No. 5 | 1 | 0 |
| Plot No. 18, 19, 45, 46 | 4 | 0 |
| Plot No. 60, 61, 62, 63, 78, 79, 80, 81 | 8 | 0 |
| Plot No. 55, 56, 57, 58, 59, 82, 83, 84, 85, 86 | 10 | 0 |
| Plot No. 4 | 1 | 0 |
| Plot No. 71 | 1 | 0 |
| Plot No. 3 | 1 | 0 |
| Plot No. 54 | 1 | 0 |
| Plot No. 69 | 1 | 0 |
| Plot No. 110 | 1 | 0 |
| Plot No. 64, 77 | 2 | 0 |
| Plot No. 10 | 1 | 0 |
| Plot No. 72 | 1 | 0 |
| Plot No. 31 | 1 | 0 |
| Plot No. 109 | 1 | 0 |
| Plot No. 32 | 1 | 0 |
| Plot No. 33 | 1 | 0 |
| Plot No. 87 | 1 | 0 |
| Plot No. 1 | 1 | 0 |
| Plot No. 2 | 1 | 0 |
| Plot No. E-1 | 1 | 0 |
| Plot No. E-2 | 1 | 0 |
| Plot No. E-3 | 1 | 0 |
| Plot No. E-4 | 1 | 0 |
| Plot No. E-5 | 1 | 0 |
| Plot No. E-6 | 1 | 0 |
| Plot No. E-7 | 1 | 0 |
| Plot No. E-8 | 1 | 0 |
| Plot No. E-9 | 1 | 0 |
| Plot No. L-1 | 1 | 0 |
| Plot No. L-2 | 1 | 0 |
| Plot No. L-3 | 1 | 0 |
| Plot No. L-4 | 1 | 0 |
| Plot No. L-5 | 1 | 0 |
| Plot No. L-6 | 1 | 0 |
| Plot No. L-7 | 1 | 0 |
| Plot No. L-8 | 1 | 0 |
| Retail Shops RC-1 to RC-11 | 11 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-02-28 | |
|---|---|---|
| Proposed completion | 2022-02-28 | |
| Revised completion | 2025-02-15 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2023-Q2 | 2023-07-31 | 40 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RAMPHOOL CHOUDHARY | |
|---|---|---|
| Type | Individual | |
| Escrow bank | Rajasthan Marudhara Gramin Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=oPHomMhLYj0Zgzb6v0igCg
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/oPHomMhLYj0Zgzb6v0igCg
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=oPHomMhLYj0Zgzb6v0igCg%3D%3D&QuarterIdEnc=bARuXJV8%2FnMwIag4VEqefw%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=qa9oxti3HAg%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- Others
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-26
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- SitePlanPath · 2022-02-27
- Site_Plan_Doc_Sanctioned
- SitePlanPath · 2022-02-27
- R1_UploadDoc · 2023-06-30 · Sign in to download
- R2_UploadDoc · 2023-06-30 · Sign in to download
- R3_UploadedPath · 2023-07-30 · Sign in to download