Overview
PRAGYA SAVITRI ENCLAVE PHASE-2
PEPPL CONSTRUCTION PVT. LTD. · Patna
Units36
Booked32 of 36As of 2026-03-31
Construction progress100%As of 2026-03-31
Completion2024-09-21Proposed
Registered on2020-12-21
Valid to2024-09-21
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 9 unit types |
| Construction & progress | 4 progress details · 21 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 31 documents · 26 source links |
Registration
Registration
| Promoter | PEPPL CONSTRUCTION PVT. LTD. | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00668-2/1292/R-1077/2020 | |
| Registered on | 2020-12-21 | |
| Valid to | 2024-09-21 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2024-09-21 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,60,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,597.77 | |
|---|---|---|
| Built-up (m²) | 3,417.89 | |
| FAR | 2.49 | |
| Towers | 1 | |
| Units | 36 | |
| Booked | 32 | |
| Booked as of | 2026-03-31 |
Unit types
| 2 BHK | 4 | PRAGYA SAVITRI ENCLAVE PHASE-2 |
| 2 BHK | 4 | PRAGYA SAVITRI ENCLAVE PHASE-2 |
| 2 BHK | 4 | PRAGYA SAVITRI ENCLAVE PHASE-2 |
| 3 BHK | 4 | PRAGYA SAVITRI ENCLAVE PHASE-2 |
| 3 BHK | 4 | PRAGYA SAVITRI ENCLAVE PHASE-2 |
| 3 BHK | 4 | PRAGYA SAVITRI ENCLAVE PHASE-2 |
| 3 BHK | 4 | PRAGYA SAVITRI ENCLAVE PHASE-2 |
| 3 BHK | 4 | PRAGYA SAVITRI ENCLAVE PHASE-2 |
| 3 BHK | 4 | PRAGYA SAVITRI ENCLAVE PHASE-2 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2026-03-31 | |
| Start | 2020-09-21 | |
| Proposed completion | 2024-09-21 |
Quarterly progress
| 2026-Q1 | 2026-05-13 | 100% | 32 |
| 2025-Q4 | 2026-01-29 | ||
| 2025-Q3 | 2025-10-31 | ||
| 2025-Q2 | 2025-08-29 | ||
| 2025-Q1 | 2025-04-29 | ||
| 2024-Q4 | 2025-01-22 | ||
| 2024-Q3 | 2025-01-22 | ||
| 2024-Q2 | 2025-01-22 | ||
| 2024-Q1 | 2024-08-19 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2024-07-25 | ||
| 2022-Q4 | 2023-02-06 | ||
| 2022-Q3 | 2022-11-28 | ||
| 2022-Q2 | 2022-10-09 | ||
| 2022-Q1 | 2022-07-07 | ||
| 2021-Q4 | 2022-03-22 | ||
| 2021-Q3 | 2022-03-22 | ||
| 2021-Q2 | 2022-03-22 | ||
| 2021-Q1 | 2022-03-22 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | PEPPL CONSTRUCTION PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP277201800668-2
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP277201800668&ld=pan&pj=RERAP277201800668-2&f=2025-2026&q=4
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP277201800668-2
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Approved Layout Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Q4 (Jan - Mar) / 2025-2026 · 2026-05-13
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-29
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-31
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-29
- Q4-Jan to Mar / 2024-2025 · 2025-04-29
- Q3-Oct to Dec / 2024-2025 · 2025-01-22
- Q2-Jun to Sep / 2024-2025 · 2025-01-22
- Q1-Apr to Jun / 2024-2025 · 2025-01-22
- Q4-Jan to Mar / 2023-2024 · 2024-08-19
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2024-07-25
- Q3-Oct to Dec / 2022-2023 · 2023-02-06
- Q2-Jul to Sep / 2022-2023 · 2022-11-28
- Q1-Apr to Jun / 2022-2023 · 2022-10-09
- Q4-Jan to Mar / 2021-2022 · 2022-07-07
- Q3-Oct to Dec / 2021-2022 · 2022-03-22
- Q2-Jul to Sep / 2021-2022 · 2022-03-22
- Q1-Apr to Jun / 2021-2022 · 2022-03-22
- Q4-Jan to Mar / 2020-2021 · 2022-03-22
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Notice of Commencement
- 2025-Q4 · 2026-01-29
- 2025-Q3 · 2025-10-31
- 2025-Q2 · 2025-08-29
- 2025-Q1 · 2025-04-29
- 2024-Q4 · 2025-01-22
- 2024-Q3 · 2025-01-22
- 2024-Q2 · 2025-01-22
- 2024-Q1 · 2024-08-19
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2024-07-25
- 2022-Q4 · 2023-02-06
- 2022-Q3 · 2022-11-28
- 2022-Q2 · 2022-10-09
- 2022-Q1 · 2022-07-07
- 2021-Q4 · 2022-03-22
- 2021-Q3 · 2022-03-22
- 2021-Q2 · 2022-03-22
- 2021-Q1 · 2022-03-22