Overview
PRECORE CITY(DDJAY)
M V BUILDCON PRIVATE LIMITED · Gurugram
Units178
Completion2023-03-12Proposed
Registered on2021-07-20
Valid to2025-03-10
Approvals9
Cases2
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Disputes & cases | 2 cases |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 2 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 17 documents · 3 source links |
Registration
Registration
| Promoter | M V BUILDCON PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/473/205/2021/41 DATED 20.07.2021 | |
| Registered on | 2021-07-20 | |
| Valid to | 2025-03-10 | |
| Status (as filed) | Registered | |
| Proposed completion | 2023-03-12 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | DULB/CTP/TP-SOHNA/2020/1996 | Town & Country Planning Department | |
| Layout Plan | 2020-03-16 | ||
| Building Plan | |||
| I. LICENCE | 2020-03-13 | ||
| II. LOI- DULB/CTP/TP-SOHNA/2019/13598-99 | 2019-09-05 | ||
| III. LAYOUT PLAN- DULB/CTP/2020/6 | 2020-03-16 | ||
| IV. SERVICE PLAN- DULB/CTP/TP-SOHNA/2020/4383-84 | 2020-07-13 | ||
| V. NOC- 10572 | 2021-03-08 | ||
| VI. ZONING PLAN- DULB/CTP/TP-SOHNA/3391-92 | 2020-05-20 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Status |
|---|---|---|
| RERA-GRG-4469-2022 | HRERA Gurugram | Disposed |
| RERA-GRG-3661-2022 | HRERA Gurugram | Pending |
Complaints & cases
| Cases | 2 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹23,41,19,999.99999997 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹40,59,80,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 33,391.624 | |
|---|---|---|
| Units | 178 |
Unit types
| Type | Carpet (m²) | Units |
|---|---|---|
| Plot | 178 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-08-13 | |
|---|---|---|
| Proposed completion | 2023-03-12 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M V BUILDCON PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/R0dNLzQ3My8yMDUvMjAyMS80MSBEQVRFRCAyMC4wNy4yMDIx
- https://haryanarera.gov.in/view_project/project_preview_open/1357
- Registration Certificate · 2021-07-20
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2021-04-19
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2021-04-19
- ZONING PLAN · 2021-04-19
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2021-04-20 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2021-04-20
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2021-04-20
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2021-04-20 · Sign in to download
- DEMARCATION PLAN · 2021-08-20
- SERVICE ESTIMATE · 2021-08-20 · Sign in to download
- SERVICE PLAN LETTER · 2021-08-20
- SUPERIMPOSED PLAN · 2021-08-20
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2021-08-20
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2021-08-20 · Sign in to download
- Extension No. 26 of 2023 dated 28.08.2023 · 2023-11-03 · Sign in to download
- PROJECT CONTINUATION- RC/REP/HARERA/GGM/41 OF 2021/7(3)/52/2024/11 DATED 09.07.2024 · 2024-07-18 · Sign in to download