Overview
PRIME TOWER, LE GARDEN (Tower P)
AJNARA REALTECH LIMITED · Gautam Buddha Nagar
Units239
Completion2022-11-29Revised · Proposed 2021-12-31
Registered on2017-12-01
Valid to2022-11-29
Approvals1
Complaints13As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 13 project complaints · 196 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 40 unit types |
| Construction & progress | 3 progress details · 17 quarters · 2 extensions |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 63 documents · 25 source links |
Registration
Registration
| Promoter | AJNARA REALTECH LIMITED | |
|---|---|---|
| District | Gautam Buddha Nagar | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ14530 | |
| Registered on | 2017-12-01 | |
| Valid to | 2022-11-29 | |
| Project type | Residential | |
| Status (as filed) | NCLT PROJECTS | |
| Proposed completion | 2021-12-31 | |
| Revised completion | 2022-11-29 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | PLG/(BP)2643/8132 | 2017-11-29 | 2022-11-29 | Greater Noida Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 13 | |
|---|---|---|
| Promoter | 196 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹67,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 9,073 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 20 | |
| Units | 239 |
Unit types
| 2 BHK | 53.38 | 4 | TOWER P | 1 |
| 2 BHK | 53.38 | 4 | TOWER P | 2 |
| 2 BHK | 46.32 | 8 | TOWER P | 2 |
| 2 BHK | 53.38 | 4 | TOWER P | 3 |
| 2 BHK | 46.32 | 8 | TOWER P | 3 |
| 2 BHK | 53.38 | 4 | TOWER P | 4 |
| 2 BHK | 53.38 | 4 | TOWER P | 5 |
| 2 BHK | 46.32 | 8 | TOWER P | 5 |
| 2 BHK | 53.38 | 4 | TOWER P | 6 |
| 2 BHK | 46.32 | 8 | TOWER P | 6 |
| 2 BHK | 53.38 | 4 | TOWER P | 7 |
| 2 BHK | 46.32 | 8 | TOWER P | 7 |
| 2 BHK | 53.38 | 4 | TOWER P | 8 |
| 2 BHK | 46.32 | 8 | TOWER P | 8 |
| 2 BHK | 53.38 | 4 | TOWER P | 9 |
| 2 BHK | 46.32 | 8 | TOWER P | 9 |
| 2 BHK | 53.38 | 4 | TOWER P | 10 |
| 2 BHK | 46.32 | 8 | TOWER P | 10 |
| 2 BHK | 46.32 | 8 | TOWER P | 11 |
| 2 BHK | 53.38 | 4 | TOWER P | 12 |
| 2 BHK | 46.32 | 8 | TOWER P | 12 |
| 2 BHK | 53.38 | 4 | TOWER P | 13 |
| 2 BHK | 46.32 | 8 | TOWER P | 13 |
| 2 BHK | 53.38 | 4 | TOWER P | 14 |
| 2 BHK | 46.32 | 8 | TOWER P | 14 |
| 2 BHK | 53.38 | 4 | TOWER P | 15 |
| 2 BHK | 53.38 | 4 | TOWER P | 16 |
| 2 BHK | 46.32 | 8 | TOWER P | 16 |
| 2 BHK | 53.38 | 4 | TOWER P | 17 |
| 2 BHK | 46.32 | 8 | TOWER P | 17 |
| 2 BHK | 53.38 | 4 | TOWER P | 18 |
| 2 BHK | 46.32 | 8 | TOWER P | 18 |
| 2 BHK | 53.38 | 4 | TOWER P | 19 |
| 2 BHK | 46.32 | 8 | TOWER P | 19 |
| 2 BHK | 53.38 | 4 | TOWER P | 20 |
| 2 BHK | 46.32 | 8 | TOWER P | 20 |
| 2 BHK | 46.32 | 7 | TOWER P | 1 |
| 2 BHK | 46.32 | 8 | TOWER P | 4 |
| 2 BHK | 53.38 | 4 | TOWER P | 11 |
| 2 BHK | 46.32 | 8 | TOWER P | 15 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-12-30 | |
|---|---|---|
| Proposed completion | 2021-12-31 | |
| Revised completion | 2022-11-29 |
Quarterly progress
| Quarter |
|---|
| 2020-Q2 |
| 2020-Q3 |
| 2020-Q4 |
| 2021-Q1 |
| 2021-Q2 |
| 2021-Q3 |
| 2021-Q4 |
| 2022-Q1 |
| 2022-Q2 |
| 2022-Q3 |
| 2022-Q4 |
| 2023-Q1 |
| 2023-Q2 |
| 2023-Q3 |
| 2023-Q4 |
| 2024-Q1 |
| 2024-Q2 |
Extensions
| Valid to | Reason |
|---|---|
| 2022-06-30 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 2022-11-29 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | AJNARA REALTECH LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | INDUSIND BANK | |
| Other projects in this city pack | 5 |
Professional firms
| Role | Firm |
|---|---|
| Engineer | OPTIMUM DESIGN PVT LTD |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=Ns/Oa4Lt1ao=&hfFlag=9emr4VdBw22M7BGjKtJWMPDI4s5cHQZP&NPJ6RAme=7OhTOma8Y6MwvKVLblpK7CEhj7eGLwTRBOBXeOWO4LnqjNSVvqvQWg==&PaURJEMAN4=ZL9MNERkNdYMQ3im5yspxQ==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/WebService1.asmx/loadNCLTprojectWithParameter
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=GAUTAM%20BUDDHA%20NAGAR
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=Ns/Oa4Lt1ao=
- View Order · Sign in to download
- Document
- Waste Disposal Plan · 2018-07-25
- Water Supply Plan · 2018-07-25
- Electricity Supply Plan · 2018-07-25
- Development Work Plan · 2018-07-25
- CA CERTIFICATE · 2018-07-30 · Sign in to download
- ARCHITECT CERTIFICATE · 2018-07-30 · Sign in to download
- ENGINEERS CERTIFICATE · 2018-07-30 · Sign in to download
- Floor plans of all types · 2017-12-01
- Floor plans of all types · 2017-12-01
- Other Plan(If Any) · 2017-12-01
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- Chartered Accountant Certificate
- Architect Certificate
- Structural Engineer Certificate
- 2020-Q2
- 2020-Q3
- 2020-Q4
- 2021-Q1
- 2021-Q2
- 2021-Q3
- 2021-Q4
- 2022-Q1
- 2022-Q2
- 2022-Q3
- 2022-Q4
- 2023-Q1
- 2023-Q2
- 2023-Q3
- 2023-Q4
- 2024-Q1
- 2024-Q2