Overview
PRIMERA (TOWER A-D) + EWS
RAMPRASTHA PROMOTERS AND DEVELOPERS PVT. LTD. · Gurugram
Completion2020-03-31Revised · Proposed 2020-03-31
Registered on2018-10-23
Valid to2025-09-30
Approvals13
Sections
| Property title & search report | |
|---|---|
| Approvals | 13 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 3 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 19 documents · 3 source links |
Registration
Registration
| Promoter | RAMPRASTHA PROMOTERS AND DEVELOPERS PVT. LTD. | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/289/2018/21 DATED 23.10.2018 | |
| Registered on | 2018-10-23 | |
| Valid to | 2025-09-30 | |
| Status (as filed) | Registered | |
| Proposed completion | 2020-03-31 | |
| Revised completion | 2020-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 12 of 2009 | Town & Country Planning Department | |
| Layout Plan | 2013-01-25 | ||
| Building Plan | 2013-01-25 | ||
| I. ENVIRONMENTAL CLEARANCE | 2014-06-30 | ||
| II. CONSENT TO ESTABLISH | 2019-02-28 | ||
| III. ARAVALI NOC | 2013-12-03 | ||
| IV. FOREST NOC | 2013-11-07 | ||
| V. WATER ASSURANCE | 2013-12-11 | ||
| VI. FIRE SCHEME APPROVAL RECEIPT | 2019-06-03 | ||
| VII. HEIGHT CLEARANCE | 2019-02-20 | ||
| VIII. BUILDING PLAN BR III | 2013-04-25 | ||
| IX. REVISED BUILDING PLAN APPROVAL BR III | 2019-03-13 | ||
| X. LICENCE RENEWAL | 2019-05-20 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹5,18,00,000 | |
|---|---|---|
| Construction | ₹1,02,27,00,000 | |
| Total | ₹2,28,47,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 15,788.79 | |
|---|---|---|
| FAR | 175 |
Unit types
| Type | Units |
|---|---|
| 1 | 43,440 |
| 2 | 1,934 |
| 3 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2020-03-31 | |
|---|---|---|
| Revised completion | 2020-03-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RAMPRASTHA PROMOTERS AND DEVELOPERS PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | AXIS BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/814
- https://nominatim.openstreetmap.org/search?q=sector+37%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2018-10-23
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2019-09-06 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-09-05
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2019-09-18 · Sign in to download
- DEMARCATION PLAN · 2019-09-05
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-09-06
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2019-09-05
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2019-09-16
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2019-09-17 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-09-16 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS SET 2 · 2019-09-16
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS SET 3 · 2019-09-16
- ZONING PLAN · 2019-09-05
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2019-09-17 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-09-03
- Extension No. RC/REP/HARERA/GGM/21 of 2018/7(3)/2022/1 Dated: 21.07.2022 · 2022-08-22 · Sign in to download
- OC uploaded for tower A, B, C,D EWS bloack, commercial shoping etc · 2023-08-08 · Sign in to download
- OC uploaded · 2023-08-08 · Sign in to download
- OC uploaded · 2024-04-15 · Sign in to download