Overview
Prozone Palms Phase-IB
M/s. Alliance Mall Developers Co. Pvt. Ltd
Units216
Completion2026-02-21Revised · Proposed 2022-02-21
Registered on2019-05-29
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 1 site detail · 1 unit type |
| Construction & progress | 2 progress details · 1 quarter · 4 extensions |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 4 documents · 4 source links |
Registration
Registration
| Promoter | M/s. Alliance Mall Developers Co. Pvt. Ltd | |
|---|---|---|
| Regulator | TNRERA | |
| Registration number | TN/11/Building/0082/2019 | |
| Registered on | 2019-05-29 | |
| Project type | Building | |
| Status (as filed) | Completed | |
| Proposed completion | 2022-02-21 | |
| Revised completion | 2026-02-21 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Details |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 216 |
|---|
Unit types
| Type | Units |
|---|---|
| Dwelling units | 216 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2022-02-21 | |
|---|---|---|
| Revised completion | 2026-02-21 |
Quarterly progress
| Quarter |
|---|
| 2025-Q3 |
Extensions
| Valid to |
|---|
| 2023-08-21 |
| 2024-08-21 |
| 2025-08-21 |
| 2026-02-21 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M/s. Alliance Mall Developers Co. Pvt. Ltd | |
|---|---|---|
| Other projects in this city pack | 1 |