Overview
PURNA KAMALA ENCLAVE
BINAYAK CONSTRUCTIONS · A.T. Road
Units21
Completion2028-06-30Proposed
Registered on2025-04-11
Valid to2029-03-19
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 4 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 29 documents · 5 source links |
Registration
Registration
| Promoter | BINAYAK CONSTRUCTIONS | |
|---|---|---|
| District | JORHAT | |
| Locality | A.T. Road | |
| Regulator | RERA Assam | |
| Registration number | RERAA JO 12 OF 2025-2026 | |
| Registered on | 2025-04-11 | |
| Valid to | 2029-03-19 | |
| Status (as filed) | Ongoing Projects | |
| Proposed completion | 2028-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Layout Plan | ||
| Building Plan | ||
| NOC/Building Permit | Jorhat Municipal Board | 2022-12-14 |
| I. APPLIED FOR |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹0 | |
|---|---|---|
| Construction | ₹36,17,80,65,00,000 | |
| Total | ₹45,76,52,52,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 802 | |
|---|---|---|
| Units | 21 |
Unit types
| Plot | 1 | |
| 3 | 100 | 10 |
| 2 | 80 | 5 |
| 2 | 60 | 5 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-04-14 | |
|---|---|---|
| Proposed completion | 2028-06-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BINAYAK CONSTRUCTIONS | |
|---|---|---|
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.assam.gov.in/admincontrol/custom_search
- https://rera.assam.gov.in/admincontrol/registered_projects/1
- https://rera.assam.gov.in/assistancecontrol/project_search_public/1
- https://rera.assam.gov.in/view_project/project_preview_open/1598
- https://rera.assam.gov.in/view_project/searchprojectDetail/1598
- Registration Certificate
- FORM B, DULY NOTARIZED · 2024-03-21 · Sign in to download
- LETTER OF AUTHORIZATION FOR AUTHORIZED SIGNATORY · 2023-03-05 · Sign in to download
- Other · 2023-03-05 · Sign in to download
- Other · 2023-03-05 · Sign in to download
- REGISTRATION CERTIFICATE OF THE ENTITY · 2023-03-05
- NO OBJECTION CERTIFICATE FROM THE COMPETENT AUTHORITY · 2023-03-05 · Sign in to download
- COMMENCEMENT CERTIFICATE OF THE PROJECT · 2023-03-05 · Sign in to download
- PLANNING PERMIT FROM COMPETENT AUTHORITY · 2023-03-05
- LOCATIONAL MAP INCLUDING LATITUDE AND LONGITUDE · 2023-03-05 · Sign in to download
- FIRE NOC · 2023-03-05
- APPROVED DRAWING FROM COMPETENT AUTHORITY · 2023-03-05 · Sign in to download
- CARPET AREA AND PARKING AREA DETAILS · 2023-03-05 · Sign in to download
- ARCHITECT, STRUCTURAL ENGINEER AND CONTRACTOR DETAILS WITH NAME AND ADDRESS AS THE CASE MAY BE · 2024-04-15 · Sign in to download
- PLAN OF DEVELOPMENT WORKS · 2024-04-15
- HEIGHT CLEARANCE FROM AIRPORT AUTHORITY OF INDIA · 2024-06-27
- PROJECT COST ESTIMATE · 2024-06-30 · Sign in to download
- PROOF CHECKING OF STRUCTURAL DESIGN / VETTING CERTIFICATE · 2024-06-30 · Sign in to download
- LATEST NON ENCUMBRANCE CERTIFICATE · 2023-03-05 · Sign in to download
- POWER OF ATTORNEY · 2023-03-05 · Sign in to download
- TRACE MAP SHOWING NEARBY BY STREAMS, PONDS ETC. · 2023-03-05 · Sign in to download
- PHOTOCOPY OF BANK DRAFT · 2024-06-21 · Sign in to download
- INCOME TAX RETURN OF THE PROMOTER FOR THE IMMEDIATELY PRECEDING THREE (3) FINANCIAL YEARS · 2024-06-26 · Sign in to download
- BANK MANAGER'S LETTER MENTIONING THAT THE ACCOUNT HAS BEEN OPENED IN COMPLIANCE WITH THE SECTION 4(2)(L)(D) OF REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016 · 2024-06-26 · Sign in to download
- LAYOUT PLAN · 2024-06-30
- SERVICE PLAN · 2024-06-30
- Project application order/letter · 2025-04-07 · Sign in to download
- Project application order/letter · 2025-02-28 · Sign in to download
- Project application order/letter · 2025-01-30 · Sign in to download