DOSLChhattisgarh Workspace

Overview

PUSHP PALLAV PHASE - VI

M/S SHRIJAN BUILDERS · KORBA
Units63
Booked40 of 63As of 2022-09-30
Construction progress100%As of 2022-09-30
Completion2022-08-29Revised · Proposed 2019-12-31
Registered on2019-04-09
Approvals4

Sections

Property title & search report
Approvals4 approvals
Contract & costs2 cost heads · 14 quarters
Technical report
Site & area3 site details · 63 unit types
Construction & progress4 progress details · 14 quarters
Developer & finance
Developer4 developer details
The evidence
Sources83 documents · 7 source links

Registration

Registration

PromoterM/S SHRIJAN BUILDERS
DistrictKORBA
RegulatorCG RERA
Registration numberPCGRERA090419000958
Registered on2019-04-09
Project typePlotted Development
Status (as filed)New
Proposed completion2019-12-31
Revised completion2022-08-29