Overview
Pushpagiriyil Santos Residency
Pushpagiriyil Builders and Developers · Near the Building No. 9/34, Paippad
Units43
Booked23 of 43
Construction progress67%
Completion2028-04-30Proposed
Registered on2023-12-13
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Technical report | |
| Site & area | 5 site details · 8 unit types |
| Construction & progress | 3 progress details · 11 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 30 documents · 5 source links |
Registration
Registration
| Promoter | Pushpagiriyil Builders and Developers | |
|---|---|---|
| District | Kottayam | |
| Locality | Near the Building No. 9/34, Paippad | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/KTM/234/2023 | |
| Registered on | 2023-12-13 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2028-04-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | A4-BA(367651)/2023 | 2023-11-08 | 2028-11-07 | Paippad Grama Panchayat Kottayam |
| Development Permit | A4-BA(178023)/2021 | 2021-07-19 | 2026-08-23 | Paippad Grama Panchayat |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,741 | |
|---|---|---|
| Built-up (m²) | 6,751 | |
| Towers | 0 | |
| Units | 43 | |
| Booked | 23 |
Unit types
| 2BHK | 8 | 3 | Pushpagiriyil Santos Residency |
| 2BHK | 8 | 1 | Pushpagiriyil Santos Residency |
| 2BHK | 8 | 4 | Pushpagiriyil Santos Residency |
| 2BHK | 1 | 1 | Pushpagiriyil Santos Residency |
| 3BHK | 8 | 6 | Pushpagiriyil Santos Residency |
| 3BHK | 8 | 6 | Pushpagiriyil Santos Residency |
| 3BHK | 1 | 1 | Pushpagiriyil Santos Residency |
| 4BHK | 1 | 1 | Pushpagiriyil Santos Residency |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 67% | |
|---|---|---|
| Start | 2023-11-08 | |
| Proposed completion | 2028-04-30 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
| 2025-2026 Q1 |
| 2025-2026 Q2 |
| 2025-2026 Q3 |
| 2025-2026 Q4 |
| 2024-2025 Q1 |
| 2024-2025 Q2 |
| 2024-2025 Q3 |
| 2024-2025 Q4 |
| 2023-2024 Q4 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Pushpagiriyil Builders and Developers | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | SBI | |
| Other projects in this city pack | 2 |
Professional firms
| Role | Firm |
|---|---|
| CA | R S P H & Associates |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/11445
- https://rera.kerala.gov.in/projects?district=597&page=3
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=tLKRLp5069y81%2BZ%2B4XvknQ74Sea87ogspGkOq4lx2nmyrwPTFWjR39ylepU4gCTnSXt6AcoyebH0ajkKBt5iUz5awQbRrIthkOhafzu2Qf9035BjH%2BG4n0npg4d6cPWLVgOqQG3C9RaN5Dds979Ug2qRNqaYwr%2BV95Ey0GL%2Btaxj0UMde76uAQ%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=11445&Division=1&UserID=30947&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2023-12-13
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-11-22
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-11-22
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-11-22
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2023-11-22
- Copy of Valid Building Permit · 2023-11-22
- Copy of Valid Development Permit (For villa projects & plot development projects) · 2023-11-22
- Detailed technical specifications to be adopted in the project · 2023-11-24 · Sign in to download
- Layout approval plan · 2023-11-24
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2023-11-22 · Sign in to download
- Other · 2023-11-22 · Sign in to download
- Clearance from Coastal Zone Management Authority · 2023-11-24 · Sign in to download
- Clearance from National Highways / Railways / Other Relevant Departments · 2023-11-24 · Sign in to download
- Concurrence / Layout Approval of LSG planning department · 2023-11-24
- Consent to establish (Clearance from Pollution Control Board) · 2023-11-24 · Sign in to download
- Initial NOC from Fire and Rescue department · 2023-11-24
- Initial NOC from Fire and Rescue department · 2023-11-24
- Permission from Water and sewerage department · 2023-11-24 · Sign in to download
- Others · 2024-05-16 · Sign in to download
- Others · 2024-05-16 · Sign in to download
- Charts and the project schedule · 2023-12-08 · Sign in to download
- List and details of common amenities · 2023-12-05 · Sign in to download
- Other Plans to be executed in the proposed project · 2024-03-13
- Plan for Drinking water service to be executed in the proposed project · 2023-11-24
- Plan for Drinking water service to be executed in the proposed project · 2023-11-24
- Plan of firefighting to be executed in the proposed project · 2023-12-05
- Plan of firefighting to be executed in the proposed project · 2023-12-08
- Plan of Use of renewable energy to be executed in the proposed project · 2023-11-24