Overview
R.K. Enclave Block A and B
Suresh Kumar Meena · Jaipur
Units95
Booked9 of 95As of 2026-06-30
Completion2025-07-31Revised · Proposed 2024-04-01
Registered on2024-09-24
Valid to2026-11-30
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 43 unit types |
| Construction & progress | 3 progress details · 1 quarter · 3 extensions |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 26 documents · 8 source links |
Registration
Registration
| Promoter | Suresh Kumar Meena | |
|---|---|---|
| District | Jaipur | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2024/3286 | |
| Registered on | 2024-09-24 | |
| Valid to | 2026-11-30 | |
| Project type | Plotted | |
| Status (as filed) | INPROGRESS | |
| Proposed completion | 2024-04-01 | |
| Revised completion | 2025-07-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,96,24,703 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹6,96,24,703 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2026-Q2 | ₹46,70,570 | ₹9,14,399 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 15,900 | |
|---|---|---|
| Built-up (m²) | 8,643.59 | |
| Towers | 97 | |
| Units | 95 | |
| Booked | 9 | |
| Booked as of | 2026-06-30 |
Unit types
| 1 (Block A) | 1 | 1 |
| 2 to 8 (Block A) | 7 | 0 |
| 9 (Block A) | 1 | 0 |
| 10 (Block A) | 1 | 1 |
| 11 to 16 (Block A) | 6 | 4 |
| 17 (Block A) | 1 | 0 |
| 18 (Block A) | 1 | 1 |
| 19 (Block A) | 1 | 0 |
| 20 to 24 (Block A) | 5 | 0 |
| 25 (Block A) | 1 | 0 |
| 26 (Block A) | 1 | 0 |
| 27 (Block A) | 1 | 0 |
| 28 (Block A) | 1 | 0 |
| 29 to 33 (Block A) | 5 | 0 |
| 34 (Block A) | 1 | 0 |
| 35 (Block A) | 1 | 0 |
| 36 (Block A) | 1 | 0 |
| 37 to 39 (Block A) | 3 | 0 |
| 40 (Block A) | 1 | 0 |
| 41 to 46 (Block A) | 6 | 0 |
| 47 (Block A) | 1 | 0 |
| SR-1 (Block A) | 1 | 0 |
| SR-2 (Block A) | 1 | 0 |
| SR-3 | 1 | 0 |
| SC-1 TO SC-2 (Block A) | 2 | 0 |
| SC-3 TO SC-7 (Block A) | 5 | 0 |
| SC-8 (Block A) | 1 | 0 |
| SC-9 to SC-13 | 5 | 0 |
| RC-1 to RC-10 (Block A) | 10 | 0 |
| 1 (Block B) | 1 | 1 |
| 2 (Block B) | 1 | 0 |
| 3 (Block B) | 1 | 1 |
| 4 (Block B) | 1 | 1 |
| 5 (Block B) | 1 | 0 |
| 6 (Block B) | 1 | 0 |
| 7 (Block B) | 1 | 0 |
| 8 (Block B) | 1 | 0 |
| 9 (Block B) | 1 | 0 |
| 10 (Block B) | 1 | 1 |
| 11 (Block B) | 1 | 0 |
| 12 (Block B) | 1 | 0 |
| 13 to 21 (Block B) | 9 | 9 |
| 22 (Block B) | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-04-01 | |
|---|---|---|
| Proposed completion | 2024-04-01 | |
| Revised completion | 2025-07-31 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2026-Q2 | 2026-07-31 | 9 |
Extensions
| Valid to |
|---|
| 2026-07-31 |
| 2026-01-31 |
| 2026-11-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Suresh Kumar Meena | |
|---|---|---|
| Type | Individual | |
| Escrow bank | INDIAN BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=jBkQbvO-i6czsGLLAFYIDQ
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/jBkQbvO-i6czsGLLAFYIDQ
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=jBkQbvO%2Bi6czsGLLAFYIDQ%3D%3D&QuarterIdEnc=lA2coA4x9us9F40n4lwpZg%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=xki1y1cHEOw%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Advocate Search Report along with Search Fee Receipt · 2025-08-29 · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · 2025-08-29 · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Other Approvals as may be required and obtained for the project (if any) · 2024-04-12
- Project Related Approval Documents (Plotted)
- FormFUploadedPathString · Sign in to download
- FormFUploadedPathString · Sign in to download
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Others
- Bankaffidavit · Sign in to download
- LayoutPlanPath · 2024-02-24
- R1_filepath · Sign in to download
- R2_filepath · Sign in to download
- R3_filepath · Sign in to download
- RERABankStatementUpload · Sign in to download
- NoLienCertificateUpload
- Extension order · Sign in to download
- Extension order · Sign in to download