Overview
RADHA FLORENCE EMPIRE
SRS FORTUNE ESTATE AND DEVELOPERS PVT. LTD. · RAIPUR
Units85
Booked49 of 85As of 2026-06-30
Construction progress76%As of 2026-06-30
Completion2027-05-31Revised · Proposed 2021-12-31
Registered on2018-09-25
Approvals1
Cases4
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 4 cases |
| Contract & costs | 2 cost heads · 32 quarters |
| Technical report | |
| Site & area | 3 site details · 85 unit types |
| Construction & progress | 4 progress details · 32 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 160 documents · 11 source links |
Registration
Registration
| Promoter | SRS FORTUNE ESTATE AND DEVELOPERS PVT. LTD. | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA250918000782 | |
| Registered on | 2018-09-25 | |
| Project type | Plotted Development | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2021-12-31 | |
| Revised completion | 2027-05-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| SM-EXA-2026-03571 | CG RERA | Complaint | Disposed | 2026-05-11 |
| SM-EXP-2025-03045 | CG RERA | Complaint | Disposed | 2025-11-26 |
| SM-EXP-2023-02099 | CG RERA | Complaint | Disposed | 2024-02-28 |
| M-COM-2019-00612 | CG RERA | Complaint | Disposed | 2019-06-14 |
Complaints & cases
| Cases | 4 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,15,74,000 | |
|---|---|---|
| Construction | ₹3,23,61,000 |
Quarterly money flows
| 2018-Q3 | ₹0 |
| 2018-Q4 | ₹10,882 |
| 2019-Q1 | ₹10,882 |
| 2019-Q2 | ₹12,413 |
| 2019-Q3 | ₹885 |
| 2019-Q4 | ₹437 |
| 2020-Q1 | ₹3,686.77 |
| 2020-Q2 | ₹2,344.51 |
| 2020-Q3 | ₹0.02 |
| 2020-Q4 | ₹1,592 |
| 2021-Q1 | ₹723.43 |
| 2021-Q2 | ₹5,266.17 |
| 2021-Q3 | ₹5,103.91 |
| 2021-Q4 | ₹4,941.65 |
| 2022-Q1 | ₹4,941.65 |
| 2022-Q2 | ₹14,027.39 |
| 2022-Q3 | ₹21,527.13 |
| 2022-Q4 | ₹21,202.61 |
| 2023-Q1 | ₹9,502.61 |
| 2023-Q2 | ₹5,000 |
| 2023-Q3 | ₹5,000 |
| 2023-Q4 | ₹4,645 |
| 2024-Q1 | ₹3,777 |
| 2024-Q2 | ₹7,906 |
| 2024-Q3 | ₹7,021 |
| 2024-Q4 | ₹5,435 |
| 2025-Q1 | ₹5,435 |
| 2025-Q2 | ₹3,666.05 |
| 2025-Q3 | ₹2,780.05 |
| 2025-Q4 | ₹1,895.05 |
| 2026-Q1 | ₹1,010.05 |
| 2026-Q2 | ₹125.05 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 85 | |
|---|---|---|
| Booked | 49 | |
| Booked as of | 2026-06-30 |
Unit types
| --1 | 1 | 1 |
| --2 | 1 | 0 |
| --3 | 1 | 0 |
| --4 | 1 | 0 |
| --5 | 1 | 0 |
| --6 | 1 | 0 |
| --7 | 1 | 0 |
| --8 | 1 | 0 |
| --9 | 1 | 0 |
| --10 | 1 | 0 |
| --11 | 1 | 0 |
| --12 | 1 | 1 |
| --13 | 1 | 1 |
| --14 | 1 | 1 |
| --15 | 1 | 0 |
| --16 | 1 | 1 |
| --17 | 1 | 1 |
| --18 | 1 | 0 |
| --19 | 1 | 0 |
| --20 | 1 | 0 |
| --21 | 1 | 1 |
| --22 | 1 | 0 |
| --23 | 1 | 1 |
| --24 | 1 | 1 |
| --25 | 1 | 1 |
| --26 | 1 | 1 |
| --27 | 1 | 1 |
| --28 | 1 | 1 |
| --29 | 1 | 0 |
| --30 | 1 | 1 |
| --31 | 1 | 1 |
| --32 | 1 | 1 |
| --33 | 1 | 1 |
| --34 | 1 | 1 |
| --35 | 1 | 1 |
| --36 | 1 | 1 |
| --37 | 1 | 1 |
| --38 | 1 | 1 |
| --39 | 1 | 1 |
| --40 | 1 | 1 |
| --41 | 1 | 1 |
| --42 | 1 | 1 |
| --43 | 1 | 1 |
| --44 | 1 | 1 |
| --45 | 1 | 1 |
| --46 | 1 | 1 |
| --47 | 1 | 1 |
| --48 | 1 | 1 |
| --49 | 1 | 1 |
| --50 | 1 | 1 |
| --51 | 1 | 1 |
| --52 | 1 | 1 |
| --53 | 1 | 1 |
| --54 | 1 | 1 |
| --55 | 1 | 1 |
| --56 | 1 | 1 |
| --57 | 1 | 1 |
| --58 | 1 | 0 |
| --59 | 1 | 0 |
| --60 | 1 | 0 |
| --61 | 1 | 0 |
| --62 | 1 | 0 |
| --63 | 1 | 1 |
| --64 | 1 | 1 |
| --65 | 1 | 1 |
| --66 | 1 | 1 |
| --67 | 1 | 1 |
| --68 | 1 | 1 |
| --69 | 1 | 0 |
| --70 | 1 | 0 |
| --71 | 1 | 1 |
| --72 | 1 | 1 |
| --73 | 1 | 0 |
| --74 | 1 | 0 |
| --75 | 1 | 0 |
| --76 | 1 | 0 |
| --77 | 1 | 0 |
| --78 | 1 | 0 |
| --79 | 1 | 0 |
| --80 | 1 | 0 |
| --81 | 1 | 0 |
| --82 | 1 | 0 |
| --83 | 1 | 0 |
| --84 | 1 | 0 |
| --85 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 76% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2021-12-31 | |
| Revised completion | 2027-05-31 |
Quarterly progress
| 2018-Q3 | 25% |
| 2018-Q4 | 25% |
| 2019-Q1 | 25% |
| 2019-Q2 | 25% |
| 2019-Q3 | 66% |
| 2019-Q4 | 66% |
| 2020-Q1 | 74% |
| 2020-Q2 | 44% |
| 2020-Q3 | 45% |
| 2020-Q4 | 75% |
| 2021-Q1 | 75% |
| 2021-Q2 | 76% |
| 2021-Q3 | 76% |
| 2021-Q4 | 76% |
| 2022-Q1 | 76% |
| 2022-Q2 | 76% |
| 2022-Q3 | 76% |
| 2022-Q4 | 76% |
| 2023-Q1 | 76% |
| 2023-Q2 | 76% |
| 2023-Q3 | 76% |
| 2023-Q4 | 76% |
| 2024-Q1 | 76% |
| 2024-Q2 | 76% |
| 2024-Q3 | 76% |
| 2024-Q4 | 76% |
| 2025-Q1 | 76% |
| 2025-Q2 | 76% |
| 2025-Q3 | 76% |
| 2025-Q4 | 76% |
| 2026-Q1 | 76% |
| 2026-Q2 | 76% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SRS FORTUNE ESTATE AND DEVELOPERS PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=ODc4
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2026-05-11 · Sign in to download
- Final order · 2025-11-26 · Sign in to download
- Final order · 2024-02-28 · Sign in to download
- Final order · 2019-06-14 · Sign in to download
- Interim order · 2025-10-06 · Sign in to download
- Interim order · 2024-01-29 · Sign in to download
- Approval Letter of Town And Country Planning
- SM-EXA-2026-03571 · Sign in to download
- SM-EXP-2025-03045 · Sign in to download
- SM-EXP-2023-02099 · Sign in to download
- M-COM-2019-00612 · Sign in to download