DOSLJaipur, Rajasthan Workspace

Overview

Radha Govind Vihar

RADHA RANI BUILDESTATE PVT LTD · Jaipur
Units63
Booked1 of 63As of 2024-03-31
Completion2026-01-31Revised · Proposed 2023-01-15
Registered on2023-01-30
Valid to2026-01-31

Sections

Property title & search report
Contract & costs3 cost heads · 1 quarter
Technical report
Site & area6 site details · 27 unit types
Construction & progress3 progress details · 1 quarter
Developer & finance
Developer4 developer details
The evidence
Sources48 documents · 6 source links

Registration

Registration

PromoterRADHA RANI BUILDESTATE PVT LTD
DistrictJaipur
RegulatorRajasthan RERA
Registration numberRAJ/P/2023/2360
Registered on2023-01-30
Valid to2026-01-31
Project typePlotted
Status (as filed)COMPLETED
Proposed completion2023-01-15
Revised completion2026-01-31