Overview
RADHE KRISHNA COMPLEX
SUNDRAM ENGICON · Patna
Units14
Completion2023-07-20Proposed
Registered on2020-02-03
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 3 unit types |
| Construction & progress | 2 progress details · 15 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 23 documents · 20 source links |
Registration
Registration
| Promoter | SUNDRAM ENGICON | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP35950-1/1043/R-891/2020 | |
| Registered on | 2020-02-03 | |
| Project type | Mixed Development(residential and commercial) | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2023-07-20 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 505.85 | |
|---|---|---|
| Built-up (m²) | 1,176.52 | |
| FAR | 2.42 | |
| Towers | 1 | |
| Units | 14 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 2 | RADHE KRISHNA COMPLEX |
| 2 BHK | 2 | RADHE KRISHNA COMPLEX |
| Shop | 10 | RADHE KRISHNA COMPLEX |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-08-20 | |
|---|---|---|
| Proposed completion | 2023-07-20 |
Quarterly progress
| 2024-Q3 | 2024-10-17 |
| 2024-Q2 | 2024-07-07 |
| 2023-Q4 | 2024-07-25 |
| 2023-Q1 | 2023-04-10 |
| 2022-Q4 | 2023-02-04 |
| 2022-Q3 | 2024-07-25 |
| 2022-Q2 | 2024-07-25 |
| 2022-Q1 | 2022-05-17 |
| 2021-Q4 | 2022-01-21 |
| 2021-Q3 | 2022-01-21 |
| 2021-Q1 | 2021-09-03 |
| 2020-Q2 | 2021-09-03 |
| 2019-Q4 | 2021-01-31 |
| 2019-Q3 | 2021-01-31 |
| 2019-Q2 | 2020-10-10 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SUNDRAM ENGICON | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Indusind Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP07242019135950-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP07242019135950-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Approved Layout Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q2-Jul to Sep / 2024-2025 · 2024-10-17
- Q1-Apr to Jun / 2024-2025 · 2024-07-07
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-10
- Q3-Oct to Dec / 2022-2023 · 2023-02-04
- Q2-Jul to Sep / 2022-2023 · 2024-07-25
- Q1-Apr to Jun / 2022-2023 · 2024-07-25
- Q4-Jan to Mar / 2021-2022 · 2022-05-17
- Q3-Oct to Dec / 2021-2022 · 2022-01-21
- Q2-Jul to Sep / 2021-2022 · 2022-01-21
- Q4-Jan to Mar / 2020-2021 · 2021-09-03
- Q1-Apr to Jun / 2020-2021 · 2021-09-03
- Q3-Oct to Dec / 2019-2020 · 2021-01-31
- Q2-Jul to Sep / 2019-2020 · 2021-01-31
- Q1-Apr to Jun / 2019-2020 · 2020-10-10
- Notice of Commencement
- 2024-Q3 · 2024-10-17
- 2024-Q2 · 2024-07-07
- 2023-Q4 · 2024-07-25
- 2023-Q1 · 2023-04-10
- 2022-Q4 · 2023-02-04
- 2022-Q3 · 2024-07-25
- 2022-Q2 · 2024-07-25
- 2022-Q1 · 2022-05-17
- 2021-Q4 · 2022-01-21
- 2021-Q3 · 2022-01-21
- 2021-Q1 · 2021-09-03
- 2020-Q2 · 2021-09-03
- 2019-Q4 · 2021-01-31
- 2019-Q3 · 2021-01-31
- 2019-Q2 · 2020-10-10