Overview
RADHE VILLA
RUDRA CONSTRUCTIONS · Patna
Units16
Booked8 of 16As of 2026-06-30
Construction progress100%As of 2026-06-30
Completion2027-06-23Proposed
Registered on2022-07-22
Valid to2027-06-23
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 1 unit type |
| Construction & progress | 4 progress details · 16 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 27 documents · 21 source links |
Registration
Registration
| Promoter | RUDRA CONSTRUCTIONS | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00178-5/133/R-1439/2022 | |
| Registered on | 2022-07-22 | |
| Valid to | 2027-06-23 | |
| Project type | Mixed Development(residential and commercial) | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2027-06-23 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Authority |
|---|---|
| Sanctioned Building Plan (MAP) | Patna Metropolitan Area Authority |
| Notice of Commencement in form X |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹76,50,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 754.43 | |
|---|---|---|
| Built-up (m²) | 1,885.31 | |
| FAR | 2.49 | |
| Towers | 1 | |
| Units | 16 | |
| Booked | 8 | |
| Booked as of | 2026-06-30 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 16 | Radhe Villa |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2026-06-30 | |
| Start | 2022-07-10 | |
| Proposed completion | 2027-06-23 |
Quarterly progress
| 2026-Q2 | 2026-07-15 | 100% | 8 |
| 2026-Q1 | 2026-04-15 | ||
| 2025-Q4 | 2026-01-15 | ||
| 2025-Q3 | 2025-10-15 | ||
| 2025-Q2 | 2025-08-16 | ||
| 2025-Q1 | 2025-04-15 | ||
| 2024-Q4 | 2025-01-15 | ||
| 2024-Q3 | 2024-10-09 | ||
| 2024-Q2 | 2024-07-15 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2023-04-15 | ||
| 2022-Q4 | 2023-04-20 | ||
| 2022-Q3 | 2022-11-17 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RUDRA CONSTRUCTIONS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 7 |
Professional firms
| Role | Firm |
|---|---|
| Architect | A R & ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP272201800178-5
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP272201800178&ld=pan&pj=RERAP272201800178-5&f=2026-2027&q=1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP272201800178-5
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-15
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-15
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-15
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-15
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-16
- Q4-Jan to Mar / 2024-2025 · 2025-04-15
- Q3-Oct to Dec / 2024-2025 · 2025-01-15
- Q2-Jul to Sep / 2024-2025 · 2024-10-09
- Q1-Apr to Jun / 2024-2025 · 2024-07-15
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-15
- Q3-Oct to Dec / 2022-2023 · 2023-04-20
- Q2-Jul to Sep / 2022-2023 · 2022-11-17
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Notice of Commencement in form X
- 2026-Q1 · 2026-04-15
- 2025-Q4 · 2026-01-15
- 2025-Q3 · 2025-10-15
- 2025-Q2 · 2025-08-16
- 2025-Q1 · 2025-04-15
- 2024-Q4 · 2025-01-15
- 2024-Q3 · 2024-10-09
- 2024-Q2 · 2024-07-15
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-15
- 2022-Q4 · 2023-04-20
- 2022-Q3 · 2022-11-17