Overview
RADIANCE ETERNITY
RADIANCE REALTY DEVELOPERS INDIA LTD · Chennai
Units215
Completion2030-05-26Proposed
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Technical report | |
| Site & area | 2 site details · 4 unit types |
| Construction & progress | 1 progress detail · 2 quarters |
| Developer & finance | |
| Developer | 3 developer details · 1 professional firm |
| The evidence | |
| Sources | 21 documents · 7 source links |
Registration
Registration
| Promoter | RADIANCE REALTY DEVELOPERS INDIA LTD | |
|---|---|---|
| District | Chennai | |
| Locality | Chennai | |
| Regulator | TNRERA | |
| Registration number | TN/29/Building/0206/2025 | |
| Project type | Building | |
| Status (as filed) | Progress of Work as on September 2026 | |
| Proposed completion | 2030-05-26 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Planning permission | File No. CMDA/PP/HRB/S/0830/2024, Planning Permission No. OL-PP/HRB/0024/2025, Permit No. OL-01829 Dated - 27.05.2025 | 2025-05-27 | 2033-05-26 | Chennai Metropolitan Development Authority |
| Building permit | CMDA/WDCN15/00224/2025 | 2025-03-28 | Greater Chennai Corporation |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 8,971.94 | |
|---|---|---|
| Units | 215 |
Unit types
| Floor Area < 60 Sq.M | 0 | ||
| Floor Area > 60 Sq.M: | 49 | Block - A | 1st Floor to 10th Floor |
| Floor Area < 60 Sq.M | 0 | ||
| Floor Area > 60 Sq.M: | 166 | Block - B | 1st Floor to 21st Floor |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2030-05-26 |
|---|
Quarterly progress
| Quarter |
|---|
| 2026-Q3 |
| 2026-Q3 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RADIANCE REALTY DEVELOPERS INDIA LTD | |
|---|---|---|
| Escrow bank | ICICI Bank | |
| Other projects in this city pack | 1 |
Professional firms
| Role | Firm |
|---|---|
| Contractor | RADIANCE REALTY DEVELOPERS INDA LTD |
Sources
Sources
Source URLs & documents
- https://rera.tn.gov.in/project-details/07660f00-3f76-11f0-aeb8-bdb4e80ef5d5
- https://rera.tn.gov.in/public-view1/building/pfirm/07643d20-3f76-11f0-b9f1-b5871e996202
- https://rera.tn.gov.in/public-view2/building/pfirm/e1138bd0-3f8e-11f0-81da-4fe668dd8bbb
- https://rera.tn.gov.in/registered-building/tn
- Document
- Progress of Work as on September 2026
- Planning Permission Approval / Renewal Letter
- Approved Plan with Local Body Seal(Upload in Readable Format)
- Building Permit Letter
- Uploaded Document · Sign in to download
- Uploaded Document · Sign in to download
- Uploaded Document · Sign in to download
- View GLV Document · Sign in to download
- Encumbrance Certificate from the date of approval of planning permission to RERA submission date
- Carpet Area Statement
- Carpet Area Statement (Duly signed by registered architect / promoter with seal)
- Structural Stability Certificate along with Structural Design Calculation (Indicating Site Address & No. of Floors as per Approved Plan)
- Design & Drawing for Structural Stability
- Declaration (Form B) · Sign in to download
- Stage of Construction & Site Photographs with date · Sign in to download
- Allotment Letter · Sign in to download
- Others · Sign in to download
- Bank statement for the last one year duly signed by the Bank to be enclosed
- Furnish the details Flat-wise
- Promoter firm registration certificate · Sign in to download
- Planning permission · 2025-05-27
- Building permit · 2025-03-28
- 2026-Q3