DOSLBihar Workspace

Overview

RAJDHANI PALACE

RAJDHANI DEVELOPERS · Patna
Booked5As of 2026-09-30
Construction progress65%As of 2026-09-30
Completion2028-06-23Proposed
Registered on2024-04-24
Valid to2028-06-23
Approvals5

Sections

Property title & search report
Approvals5 approvals
Contract & costs1 cost head
Technical report
Site & area6 site details
Construction & progress4 progress details · 10 quarters
Developer & finance
Developer4 developer details
The evidence
Sources21 documents · 14 source links

Registration

Registration

PromoterRAJDHANI DEVELOPERS
DistrictPatna
RegulatorRERA Bihar
Registration numberBRERAP12637-001/34/R-1682/2024
Registered on2024-04-24
Valid to2028-06-23
Project typeMixed
Status (as filed)RERA Registered Projects
Proposed completion2028-06-23