Overview
Rajeshwar Enclave
Sri Khelari Builders and Construction Pvt.Ltd · Patna
Units144
Completion2025-12-31Proposed
Registered on2022-03-30
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 3 unit types |
| Construction & progress | 2 progress details · 8 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 16 documents · 13 source links |
Registration
Registration
| Promoter | Sri Khelari Builders and Construction Pvt.Ltd | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00099-4/127/R-1319/2022 | |
| Registered on | 2022-03-30 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2025-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Date | Authority |
|---|---|---|
| Sanctioned Building Plan (MAP) | 2021-10-08 | Nagar Parishad Danapur Nizamat |
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹8,76,86,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 5,461.03 | |
|---|---|---|
| Built-up (m²) | 12,942.93 | |
| FAR | 2.37 | |
| Towers | 5 | |
| Units | 144 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 94 | Rajeshwar Enclave |
| 1 BHK | 40 | Rajeshwar Enclave |
| 2 BHK | 10 | Rajeshwar Enclave |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-11-15 | |
|---|---|---|
| Proposed completion | 2025-12-31 |
Quarterly progress
| 2025-Q1 | 2025-05-16 |
| 2024-Q4 | 2025-01-15 |
| 2024-Q3 | 2024-10-15 |
| 2024-Q2 | 2024-07-07 |
| 2024-Q1 | 2024-07-25 |
| 2023-Q4 | 2024-07-25 |
| 2023-Q3 | 2024-07-25 |
| 2023-Q2 | 2024-07-25 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Sri Khelari Builders and Construction Pvt.Ltd | |
|---|---|---|
| Type | Company | |
| Escrow bank | CENTRAL BANK OF INDIA | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP3012201700099-4
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP3012201700099-4
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Approved Layout Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Q4-Jan to Mar / 2024-2025 · 2025-05-16
- Q3-Oct to Dec / 2024-2025 · 2025-01-15
- Q2-Jul to Sep / 2024-2025 · 2024-10-15
- Q1-Apr to Jun / 2024-2025 · 2024-07-07
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Notice of Commencement
- 2025-Q1 · 2025-05-16
- 2024-Q4 · 2025-01-15
- 2024-Q3 · 2024-10-15
- 2024-Q2 · 2024-07-07
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25