Overview
RAJLAXXMI PARK
Overview
RAJLAXXMI PARK
Overview
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | – |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Developer's project loan | ₹3.00 Cr secured |
|---|
Approvals
| Layout approval | 1 filed · latest filed 24 Apr 2024 |
|---|
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 30 Apr 2031 |
Disputes & cases
Builder: SAPHALE LAND DEVELOPERS LLP
The filing names no land owners, so there is no name to search.
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| None listed. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Search pending. | |||||||
MahaRERA lists complaints by case number. A complaint that names this registration is listed here.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
This is the only registration under this promoter's exact name in Maharashtra.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Carpet area | Units filed | Sold | Unsold | Median ₹/sq ft carpet |
|---|---|---|---|---|
| 136–149 sq ft · 12.7–13.8 sq m | 5 | 0 | 3 | – |
| 154–244 sq ft · 14.3–22.6 sq m | 10 |
Location & risks
| Nearest mapped waterway or drain | None mapped within 3 km | |
|---|---|---|
| Nearest mapped inland water body | about 2 km, an unnamed pond |
Construction & progress
Developer
Loan & collateral
| Developer's project loan | ₹3.00 Cr secured |
|---|
Data room
Source: MahaRERA project page and the documents filed there, as read by us. 72 documents filed with MahaRERA, identity papers and photographs, are left out of this list.
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
Mapped waterways, water bodies, roads and transport stations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed 1 km ring is a visual guide; the filing supplies no measured uncertainty.
All projects in Palghar → · All projects in Maharashtra → (12 of 1,291 shown here)
Everything here is as filed by the promoter with MahaRERA, and can be stale or wrong at source. Verify against certified records before you transact.
| Registration number | P99000056103 | |
|---|---|---|
| Registered | 10 May 2024 |
| 7 |
| – |
| 254–344 sq ft · 23.6–31.9 sq m | 176 | 19 | 123 | ₹6,643 |
| 366–371 sq ft · 34.0–34.5 sq m | 46 | 3 | 30 | ₹5,823 |
| 465–528 sq ft · 43.2–49.1 sq m | 103 | 22 | 47 | ₹5,469 |
| 1,432 sq ft · 133.00 sq m | 1 | 0 | 1 | – |
| Building | Units filed | Sold | Median ₹/sq ft carpet |
|---|---|---|---|
| BLDG NO 1 WING A AND B | 87 | 1 | – |
| BLDG NO 2 | 32 | 2 | – |
| BLDG NO 3 WING A AND B | 59 | 12 | ₹5,757 |
| BLDG NO 4 WING A AND B | 91 | 24 | ₹5,545 |
| BLDG NO 5 | 43 | 5 | ₹5,823 |
| HOUSING FOR THE AFFECTED PEOPLE | 29 | 0 | – |
| Carpet area | Unsold units | Carpet area, total |
|---|---|---|
| 136–149 sq ft · 12.7–13.8 sq m | 3 | 420 sq ft |
| 154–244 sq ft · 14.3–22.6 sq m | 7 | 1,254 sq ft |
| 254–344 sq ft · 23.6–31.9 sq m | 123 | 38,750 sq ft |
| 366–371 sq ft · 34.0–34.5 sq m | 30 | 11,096 sq ft |
| 465–528 sq ft · 43.2–49.1 sq m | 47 | 23,575 sq ft |
| 1,432 sq ft · 133.00 sq m | 1 | 1,432 sq ft |
| All unsold | 211 | 76,527 sq ft |
| Projects within 4 km, counted | 18 (18 with an approximate location) | |
|---|---|---|
| Flats in them | 1,091 | |
| Sold or booked | 472 of 1,091 (43%) | |
| Unsold | 619 |
Map of mapped waterways and water bodies within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed 1 km ring is a visual guide; the filing supplies no measured uncertainty.
Mapped waterways, water bodies, roads and transport stations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed 1 km ring is a visual guide; the filing supplies no measured uncertainty.
| Nearest mapped waterway or drain | None mapped within 3 km |
|---|
| Landfill or waste transfer station | None mapped within 3 km | |
|---|---|---|
| Sewage treatment plant | None mapped within 3 km | |
| Quarry | None mapped within 3 km | |
| Crematorium | None mapped within 3 km | |
| Prison | None mapped within 3 km | |
| Electrical substation | None mapped within 3 km |
| RERA completion date | 30 Apr 2031 | |
|---|---|---|
| Registered | 10 May 2024 | |
| Completion date first filed | 31 Dec 2030 |
Land · ₹1.40 Cr 2.9%Development · ₹47.68 Cr 97.1%
| Estimated cost, at registration | ₹49.08 Cr |
|---|
Sold 17.3%Unsold 82.7%
| Units filed | 341 | |
|---|---|---|
| Sold | 44 · 13% | |
| Unsold | 211 |
| Escrow balance | ₹25,200 (INR) | |
|---|---|---|
| Filed withdrawal amount | ₹16,77,103 (INR) |