Overview
RAJPATH BALAJI ENCLAVE
Maha Lakshmi Real Estate · Ludhiana
Units364
Completion2029-03-27Proposed
Valid to2029-03-27
Approvals13
Sections
| Property title & search report | |
|---|---|
| Approvals | 13 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 20 unit types |
| Construction & progress | 2 progress details · 9 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 26 documents · 25 source links |
Registration
Registration
| Promoter | Maha Lakshmi Real Estate | |
|---|---|---|
| District | Ludhiana | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-LDH45-PR1056 | |
| Valid to | 2029-03-27 | |
| Project type | (1) Commercial (Plotted Development) (2) Residential (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2029-03-27 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Clearances (Received) | 2025-05-26 |
| CLU Certificate | ||
| CLU Certificate | ||
| Electric Substation NOC | 2025-09-16 | |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2025-05-26 |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2023-09-20 | |
| Other Document (NOC Building and Roads) | 2023-09-22 | |
| Other Document (NOC Forest) | 2023-09-26 | |
| Other Document (NOC Irrigation) | 2023-09-29 | |
| Other Document (NOC PSTCL) | 2023-10-03 | |
| Pollution Clearance from Punjab Pollution Control Board | 2025-05-27 | |
| Consent details of actual owner of Land |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹20,62,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 94,772.308 | |
|---|---|---|
| Units | 364 |
Unit types
| Plot | 98.23 | 1 | RESS PLOT NO 1 |
| Ress Plots | 1,839.2 | 20 | RESS PLOT NO 2 TO 21 |
| Ress Plots | 3,994.073 | 32 | RESS PLOT NO 22 25 TO 54 57 |
| Ress Plots | 5,956.5 | 57 | RESS PLOT NO 61 TO 101 130TO 145 |
| Ress Plot | 101.883 | 1 | RESS PLOT NO 174 |
| Ress Plot | 87.604 | 1 | RESS PLOT NO 175 |
| Ress Plot | 75.24 | 1 | RESS PLOT NO 176 |
| Ress Plots | 2,327.615 | 37 | RESS PLOT NO 60 102 179TO 213 |
| Ress Plots | 1,414.512 | 12 | RESS PLOT NO 214TO225 |
| Ress Plots | 654.888 | 6 | RESS PLOT NO 226TO 231 |
| Ress Plots | 6,771.6 | 54 | RESS PLOT NO 232 TO 285 |
| Ress Plots | 122.616 | 1 | RESS PLOT NO 286 |
| Ress Plots | 1,287.44 | 11 | RESS PLOT NO 287 TO 297 |
| Ress Plots | 1,943.75 | 18 | RESS PLOT NO 298 TO 315 |
| Ress Plot | 102.585 | 1 | RESS PLOT NO 316 |
| 2 | 158.84 | 2 | RESS PLOT NO 129 146 |
| Commercial Plots | 808.161 | 10 | COMMERCIAL SITE 1 PLOT NO 1 TO 10 |
| Plots commercial | 2,551.923 | 38 | COMMERCIAL SITE 2 PLOTS NO 01 TO 38 |
| Ress Plots | 4,765.2 | 57 | RESS PLOT NO 58 59 103 104TO128 147TO173 177 178 |
| Ress Plots | 399.407 | 4 | RESS PLOT NO 23 24 55 56 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-03-28 | |
|---|---|---|
| Proposed completion | 2029-03-27 |
Quarterly progress
| 2024-Q3 | 2025-05-18 |
| 2024-Q4 | 2025-05-18 |
| 2025-Q1 | 2025-05-18 |
| 2025-Q2 | 2025-10-15 |
| 2025-Q3 | 2025-10-15 |
| 2025-Q4 | 2026-01-15 |
| 2026-Q1 | 2026-04-15 |
| 2026-Q2 | 2026-07-15 |
| 2026-Q3 | 2026-10-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Maha Lakshmi Real Estate | |
|---|---|---|
| Type | Other | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12012&inPromoter_ID=2896&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-05-26
- CLU Certificate
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2025-09-16
- Environment Clearance certificate/ NOC · 2025-05-26
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2023-09-20
- Other Document (NOC Building and Roads) · 2023-09-22
- Other Document (NOC Forest) · 2023-09-26
- Other Document (NOC Irrigation) · 2023-09-29
- Other Document (NOC PSTCL) · 2023-10-03
- Pollution Clearance from Punjab Pollution Control Board · 2025-05-27
- Consent details of actual owner of Land
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-05-26
- CLU Certificate
- CLU Certificate
- Electric Substation NOC · 2025-09-16
- Environment Clearance certificate/ NOC · 2025-05-26
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2023-09-20
- Other Document (NOC Building and Roads) · 2023-09-22
- Other Document (NOC Forest) · 2023-09-26
- Other Document (NOC Irrigation) · 2023-09-29
- Other Document (NOC PSTCL) · 2023-10-03
- Pollution Clearance from Punjab Pollution Control Board · 2025-05-27
- Consent details of actual owner of Land
- 2024-Q3 · 2025-05-18
- 2024-Q4 · 2025-05-18
- 2025-Q1 · 2025-05-18
- 2025-Q2 · 2025-10-15
- 2025-Q3 · 2025-10-15
- 2025-Q4 · 2026-01-15
- 2026-Q1 · 2026-04-15
- 2026-Q2 · 2026-07-15
- 2026-Q3 · 2026-10-15