DOSLChhattisgarh Workspace

Overview

RALAS ROYAL PARK

RALAS BUILDERS AND DEVELOPERS · DURG
Units662
Booked594 of 662As of 2020-12-31
Construction progress100%As of 2020-12-31
Completion2021-06-30Revised · Proposed 2020-12-31
Registered on2018-07-17
Approvals1
Cases3

Sections

Property title & search report
Approvals1 approval
Disputes & cases3 cases
Contract & costs2 cost heads · 10 quarters
Technical report
Site & area3 site details · 1 unit type
Construction & progress4 progress details · 10 quarters
Developer & finance
Developer4 developer details
The evidence
Sources47 documents · 9 source links

Registration

Registration

PromoterRALAS BUILDERS AND DEVELOPERS
DistrictDURG
RegulatorCG RERA
Registration numberPCGRERA170718000580
Registered on2018-07-17
Project typePlotted Development
Status (as filed)Ongoing
Proposed completion2020-12-31
Revised completion2021-06-30