Overview
RAM AWAS-IV
SHUBHASHISH BUILDERS AND DEVELOPERS PRIVATE LIMITED · Jaipur
Units16
Booked3 of 16As of 2025-03-31
Completion2025-03-31Revised · Proposed 2023-01-01
Registered on2023-01-11
Valid to2025-03-31
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 7 site details · 4 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 29 documents · 6 source links |
Registration
Registration
| Promoter | SHUBHASHISH BUILDERS AND DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| District | Jaipur | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2023/2338 | |
| Registered on | 2023-01-11 | |
| Valid to | 2025-03-31 | |
| Project type | Group Housing | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2023-01-01 | |
| Revised completion | 2025-03-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹93,81,195 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹2,33,81,195 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2025-Q1 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 511 | |
|---|---|---|
| Built-up (m²) | 1,177.76 | |
| Towers | 16 | |
| Maximum floors | 2 | |
| Units | 16 | |
| Booked | 3 | |
| Booked as of | 2025-03-31 |
Unit types
| EWS (1 BHK) | 29.46 | 4 | 0 | RAM AWAS-IV |
| EWS (1 BHK) | 29.46 | 4 | 0 | RAM AWAS-IV |
| LIG (2 BHK) | 41.15 | 4 | 0 | RAM AWAS-IV |
| LIG (2 BHK) | 41.15 | 4 | 0 | RAM AWAS-IV |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-01-01 | |
|---|---|---|
| Proposed completion | 2023-01-01 | |
| Revised completion | 2025-03-31 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2025-Q1 | 2025-04-25 | 3 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHUBHASHISH BUILDERS AND DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 6 |
Professional firms
| Role | Firm |
|---|---|
| Architect | MA ARCHICTECTS PRIVATE LIMITED |
| CA | Ramanand Goyal and Company |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=xcqNMyANqe3ieqr8q921xg
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/xcqNMyANqe3ieqr8q921xg
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=xcqNMyANqe3ieqr8q921xg%3D%3D&QuarterIdEnc=LWcAxjcc7ZCHqgBg2%2BHu5w%3D%3D&PT=1&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=FymMB21TLKk%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Other than Plotted)
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Fire Fighting Provision
- Others
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · 2025-04-10 · Sign in to download
- R2_UploadDoc · 2025-04-16 · Sign in to download
- R3_UploadedPath · 2025-04-25 · Sign in to download
- RERAretentionAccount_UploadedPath · Sign in to download