RAMA GREENS

RAMA BUILDCON · RAIPUR
Construction progress98%As of 2026-06-30
Completion2027-07-30Revised · Proposed 2024-06-30
Registered on2019-11-27
Approvals4
Cases2

Sections

Property title & search report
Approvals4 approvals
Disputes & cases2 cases
Contract & costs2 cost heads · 27 quarters
Technical report
Site & area212 unit types
Construction & progress4 progress details · 27 quarters
Developer & finance
Developer3 developer details
The evidence
Sources180 documents · 11 source links

Registration

Registration

PromoterRAMA BUILDCON
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA271119001078
Registered on2019-11-27
Project typeGroup Housing
Status (as filed)New
Proposed completion2024-06-30
Revised completion2027-07-30