Overview
RAMAA ESTATE-IInd
KRISHNAA BALRAM RESIDENCY PRIVATE LIMITED · Jaipur
Units36
Booked21 of 36As of 2024-03-31
Completion2024-06-10Revised · Proposed 2023-05-15
Registered on2023-06-22
Valid to2024-06-10
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 20 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 42 documents · 7 source links |
Registration
Registration
| Promoter | KRISHNAA BALRAM RESIDENCY PRIVATE LIMITED | |
|---|---|---|
| District | Jaipur | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2023/2584 | |
| Registered on | 2023-06-22 | |
| Valid to | 2024-06-10 | |
| Project type | Plotted | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2023-05-15 | |
| Revised completion | 2024-06-10 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹5,86,44,779 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹7,36,44,779 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2024-Q1 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 6,380 | |
|---|---|---|
| Built-up (m²) | 3,839.44 | |
| Towers | 36 | |
| Units | 36 | |
| Booked | 21 | |
| Booked as of | 2024-03-31 |
Unit types
| Plot No. 1 | 1 | 0 |
| Plot No. 2 | 1 | 0 |
| Plot No. 3 | 1 | 0 |
| Plot No. 4 | 1 | 0 |
| Plot No. 5 | 1 | 0 |
| Plot No. 6 | 1 | 0 |
| Plot No. 7 | 1 | 0 |
| Plot No. 8 | 1 | 0 |
| Plot No. 9 | 1 | 0 |
| Plot No. 10 | 1 | 0 |
| Plot No. 11 | 1 | 0 |
| Plot No. 12 | 1 | 0 |
| Plot No. 13 | 1 | 0 |
| Plot No. 14 | 1 | 0 |
| Plot No. 15 | 1 | 0 |
| Plot No. 16 | 1 | 0 |
| Plot No. 17 | 1 | 0 |
| Plot No. 18 to 31 | 14 | 0 |
| Plot No. 32 | 1 | 0 |
| Informal Commercial Plot No. S-1 to S-4 | 4 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-05-15 | |
|---|---|---|
| Proposed completion | 2023-05-15 | |
| Revised completion | 2024-06-10 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2024-Q1 | 2024-05-03 | 21 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | KRISHNAA BALRAM RESIDENCY PRIVATE LIMITED | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | AXIS BANK | |
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://nominatim.openstreetmap.org/search?q=sirsi%2C+Jaipur%2C+Rajasthan%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- https://rera.rajasthan.gov.in/ProjectDetail?id=OPw5V-B8wEpWta_2WciuFw
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/OPw5V-B8wEpWta_2WciuFw
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=OPw5V%2BB8wEpWta%2F2WciuFw%3D%3D&QuarterIdEnc=Nj9U%2FLZCLu7pS04J0BaBRA%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=LPsNyhUrr1M%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan · 2023-06-10
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Others
- SitePlanPath · 2023-06-10
- LayoutPlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- SitePlanPath · 2023-06-10
- Site_Plan_Doc_Sanctioned
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · 2024-03-15 · Sign in to download
- R2_UploadDoc · 2024-03-15 · Sign in to download
- R3_UploadedPath · 2024-04-18 · Sign in to download
- RERAretentionAccount_UploadedPath · Sign in to download