Overview
Redbrick Manni Residency
REDBRICK HOME PRIVATE LIMITED · Patna
Units16
Booked5 of 16As of 2026-09-30
Construction progress20%As of 2026-09-30
Completion2029-11-14Proposed
Registered on2024-12-16
Valid to2029-11-14
Approvals3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 3 unit types |
| Construction & progress | 4 progress details · 8 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 18 documents · 13 source links |
Registration
Registration
| Promoter | REDBRICK HOME PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP34843-1/168/R-1787/2024 | |
| Registered on | 2024-12-16 | |
| Valid to | 2029-11-14 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2029-11-14 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Authority |
|---|---|
| Sanctioned Building Plan (MAP) | Patna Metropolitan Area Authority |
| Notice of Commencement in form X | |
| Other approval | NO |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹10,00,00,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 518.36 | |
|---|---|---|
| Built-up (m²) | 1,209 | |
| FAR | 2.36 | |
| Towers | 1 | |
| Units | 16 | |
| Booked | 5 | |
| Booked as of | 2026-09-30 |
Unit types
| Type | Units | Tower |
|---|---|---|
| Convenience Store | 2 | Redbrick Manni Residency |
| 3 BHK | 4 | Redbrick Manni Residency |
| 2 BHK | 10 | Redbrick Manni Residency |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 20% | |
|---|---|---|
| As of | 2026-09-30 | |
| Start | 2024-11-15 | |
| Proposed completion | 2029-11-14 |
Quarterly progress
| 2026-Q3 | 2026-10-11 | 20% | 5 |
| 2026-Q2 | 2026-07-15 | ||
| 2026-Q1 | 2026-04-14 | ||
| 2025-Q4 | 2026-01-15 | ||
| 2025-Q3 | 2025-10-14 | ||
| 2025-Q2 | 2025-08-20 | ||
| 2025-Q1 | 2025-04-14 | ||
| 2024-Q4 | 2025-01-14 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | REDBRICK HOME PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | IDBI Bank | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP08022024134843-1
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP08022024134843&ld=pan&pj=RERAP08022024134843-1&f=2026-2027&q=2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP08022024134843-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Declaration (Form B) · Sign in to download
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q2 (Jul - Sep) / 2026-2027 · 2026-10-11
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-15
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-14
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-15
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-14
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-20
- Q4-Jan to Mar / 2024-2025 · 2025-04-14
- Q3-Oct to Dec / 2024-2025 · 2025-01-14
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Notice of Commencement in form X
- 2026-Q2 · 2026-07-15
- 2026-Q1 · 2026-04-14
- 2025-Q4 · 2026-01-15
- 2025-Q3 · 2025-10-14
- 2025-Q2 · 2025-08-20
- 2025-Q1 · 2025-04-14
- 2024-Q4 · 2025-01-14