Overview
REDWOOD ZION
REDWOOD DEVELOPERS · Scheme Xaviers Arcade II, Jagatpura
Units48
Booked0 of 48As of 2023-06-30
Completion2025-10-10Revised · Proposed 2022-10-10
Registered on2022-12-24
Valid to2025-10-10
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 8 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 29 documents · 6 source links |
Registration
Registration
| Promoter | REDWOOD DEVELOPERS | |
|---|---|---|
| District | Jaipur | |
| Locality | Scheme Xaviers Arcade II, Jagatpura | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2022/2303 | |
| Registered on | 2022-12-24 | |
| Valid to | 2025-10-10 | |
| Project type | Group Housing | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2022-10-10 | |
| Revised completion | 2025-10-10 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,82,89,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹9,85,89,000 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2023-Q2 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,110.15 | |
|---|---|---|
| Built-up (m²) | 4,539.63 | |
| Towers | 48 | |
| Units | 48 | |
| Booked | 0 | |
| Booked as of | 2023-06-30 |
Unit types
| 2BHK (Ground, 1st, 2nd, 3rd, 4th and 5th floor) (Flat No. 102-602) | 51.44 | 6 | 0 | REDWOOD ZION |
| 2BHK (Ground, 1st, 2nd, 3rd, 4th and 5th floor) (Flat No. 104-604) | 48.7 | 6 | 0 | REDWOOD ZION |
| 2BHK (Ground, 1st, 2nd, 3rd, 4th and 5th floor) (Flat No. 106-606) | 51.44 | 6 | 0 | REDWOOD ZION |
| 3BHK (Ground, 1st, 2nd, 3rd, 4th and 5th floor) (Flat No. 101-601) | 74.4 | 6 | 0 | REDWOOD ZION |
| 3BHK (Ground, 1st, 2nd, 3rd, 4th and 5th floor) (Flat No. 103-603) | 69.02 | 6 | 0 | REDWOOD ZION |
| 3BHK (Ground, 1st, 2nd, 3rd, 4th and 5th floor) (Flat No. 105-605) | 69.15 | 6 | 0 | REDWOOD ZION |
| 3BHK (Ground, 1st, 2nd, 3rd, 4th and 5th floor) (Flat No. 107-607) | 74.58 | 6 | 0 | REDWOOD ZION |
| 3BHK (Ground, 1st, 2nd, 3rd, 4th and 5th floor) (Flat No. 108-608) | 69.1 | 6 | 0 | REDWOOD ZION |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-10-10 | |
|---|---|---|
| Proposed completion | 2022-10-10 | |
| Revised completion | 2025-10-10 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2023-Q2 | 2023-07-29 | 0 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | REDWOOD DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 3 |
Professional firms
| Role | Firm |
|---|---|
| Engineer | Prime Tech Design Consultants |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=xBwy0cbIKrzytdKoXkvh2Q
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/xBwy0cbIKrzytdKoXkvh2Q
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=xBwy0cbIKrzytdKoXkvh2Q%3D%3D&QuarterIdEnc=bARuXJV8%2FnMwIag4VEqefw%3D%3D&PT=1&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=FXkJwQF0R64%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- NOC for fire
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Other than Plotted)
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Fire Fighting Provision
- Others
- RCertificate
- ArticleAssociation · Sign in to download
- unitsPlanPath
- R1_UploadDoc · Sign in to download
- R2_UploadDoc · Sign in to download
- R3_UploadedPath · Sign in to download