Overview
REGAL HEIGHTS
GILL DEVELOPERS AND PROMOTORS PRIVATE LIMITED · Sahibzada Ajit Singh Nagar (Mohali)
Units117
Completion2026-06-30Proposed
Valid to2027-03-26
Approvals16
Sections
| Property title & search report | |
|---|---|
| Approvals | 16 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 21 unit types |
| Construction & progress | 2 progress details · 18 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 76 documents · 35 source links |
Registration
Registration
| Promoter | GILL DEVELOPERS AND PROMOTORS PRIVATE LIMITED | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PR0799 | |
| Valid to | 2027-03-26 | |
| Project type | (1) Residential (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2026-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| CLU Certificate | ||
| CLU Certificate | ||
| Environment Clearance certificate/ NOC | 2011-06-29 | |
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2021-07-02 | |
| NOC from Mining Department | 2006-07-28 | |
| Other Document (CLARIFICATION FOR NOC) | Permissions (Received) | 2021-12-31 |
| Other Document (NOC FOR CONSTRUCTION) | 2010-01-22 | |
| Other Document (REGARDING NOC) | 2021-12-09 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹57,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 4,976.0447 | |
|---|---|---|
| Towers | 3 | |
| Maximum floors | 14 | |
| Units | 117 |
Unit types
| 4 BHK Penthouse 13 and 14 Floor (Type G) | 124.409 | 1 | TOWER 10 |
| 5 BHK Penthouse 13 and 14 Floor (Type H) | 138.414 | 1 | TOWER 10 |
| 5 BHK Penthouse 13 and 14 Floor (Type I) | 141.69 | 1 | TOWER 10 |
| 4 BHK - 1-12th Floor (Type I) | 117.822 | 12 | TOWER 10 |
| 3 BHK - 1-12th Floor (Type G) | 96.669 | 12 | TOWER 10 |
| 4 BHK - 1-12th Floor (Type H) | 114.882 | 12 | TOWER 10 |
| 3 BHK 1-12th Floor (Type D) | 89.774 | 12 | TOWER 11 |
| 3 BHK 1-12th Floor (Type E) | 89.957 | 12 | TOWER 11 |
| 3 BHK 1-12th Floor (Type F) | 90.75 | 12 | TOWER 11 |
| 4 BHK Penthouse 13-14th Floor (Type D) | 113.052 | 1 | TOWER 11 |
| 4 BHK Penthouse 13-14th Floor (Type E) | 113.417 | 1 | TOWER 11 |
| 4 BHK Penthouse 13-14th Floor (Type F) | 114.21 | 1 | TOWER 11 |
| 3 BHK 1-5th Floor (Type A) | 90.516 | 5 | TOWER 12 |
| 3 BHK 1-5th Floor (Type B) | 89.603 | 5 | TOWER 12 |
| 3 BHK 1-5th Floor (Type C) | 89.736 | 5 | TOWER 12 |
| 1 BHK 6-12th Floor (Type J) | 56.455 | 7 | TOWER 12 |
| 1 BHK 6-12th Floor (Type K) | 56.976 | 7 | TOWER 12 |
| 1 BHK 6-12th Floor (Type L) | 56.385 | 7 | TOWER 12 |
| 2 BHK Penthouse 13-14th Floor (Type J) | 79.695 | 1 | TOWER 12 |
| 2 BHK Penthouse 13-14th Floor (Type K) | 80.018 | 1 | TOWER 12 |
| 2 BHK Penthouse 13-14th Floor (Type L) | 79.555 | 1 | TOWER 12 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-06-30 | |
|---|---|---|
| Proposed completion | 2026-06-30 |
Quarterly progress
| 2022-Q2 | 2022-09-28 |
| 2022-Q3 | 2022-10-10 |
| 2022-Q4 | 2023-01-28 |
| 2023-Q1 | 2023-05-24 |
| 2023-Q2 | 2023-08-21 |
| 2023-Q3 | 2023-11-17 |
| 2023-Q4 | 2024-03-26 |
| 2024-Q1 | 2024-04-09 |
| 2024-Q2 | 2024-08-24 |
| 2024-Q3 | 2024-12-14 |
| 2024-Q4 | 2025-01-13 |
| 2025-Q1 | 2025-04-10 |
| 2025-Q2 | 2025-07-15 |
| 2025-Q3 | 2025-11-05 |
| 2025-Q4 | 2026-01-24 |
| 2026-Q1 | 2026-04-21 |
| 2026-Q2 | 2026-07-10 |
| 2026-Q3 | 2026-10-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GILL DEVELOPERS AND PROMOTORS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11356&inPromoter_ID=2209&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- CLU Certificate
- CLU Certificate
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Environment Clearance certificate/ NOC · 2011-06-29
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2021-07-02
- NOC from Mining Department · 2006-07-28
- Other Document (CLARIFICATION FOR NOC) · 2021-12-31
- Other Document (NOC FOR CONSTRUCTION) · 2010-01-22
- Other Document (REGARDING NOC) · 2021-12-09
- Other Document (REGARDING THE PROJECT) · 2021-11-01 · Sign in to download
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- CLU Certificate
- CLU Certificate
- Environment Clearance certificate/ NOC · 2011-06-29
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2021-07-02
- NOC from Mining Department · 2006-07-28
- Other Document (NOC FOR CONSTRUCTION) · 2010-01-22
- Other Document (REGARDING NOC) · 2021-12-09
- 2022-Q2 · 2022-09-28
- 2022-Q3 · 2022-10-10
- 2022-Q4 · 2023-01-28
- 2023-Q1 · 2023-05-24
- 2023-Q2 · 2023-08-21
- 2023-Q3 · 2023-11-17
- 2023-Q4 · 2024-03-26
- 2024-Q1 · 2024-04-09
- 2024-Q2 · 2024-08-24
- 2024-Q3 · 2024-12-14
- 2024-Q4 · 2025-01-13
- 2025-Q1 · 2025-04-10
- 2025-Q2 · 2025-07-15
- 2025-Q3 · 2025-11-05
- 2025-Q4 · 2026-01-24
- 2026-Q1 · 2026-04-21
- 2026-Q2 · 2026-07-10
- 2026-Q3 · 2026-10-15