REIGATE FINSBURY PARK
REIGATEBUILDERSPRIVATELIMITED · NEAR MALABAR CHRISTIAN COLLEGE
Units60
Booked60 of 60
Construction progress99%As of 2023-10-20
Completion2027-02-27Proposed
Registered on2022-11-03
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Technical report | |
| Site & area | 5 site details · 1 unit type |
| Construction & progress | 4 progress details · 16 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 32 documents · 5 source links |
Registration
Registration
| Promoter | REIGATEBUILDERSPRIVATELIMITED | |
|---|---|---|
| District | Kozhikode | |
| Locality | NEAR MALABAR CHRISTIAN COLLEGE | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/KKD/181/2022 | |
| Registered on | 2022-11-03 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2027-02-27 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | TP9/28418/2022 | 2022-09-02 | 2027-09-02 | KOZHIKODE |
| Development Permit | TP/09/28418/2022 | 2022-09-02 | 2027-09-02 | KOZHIKODE |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,825.9 | |
|---|---|---|
| Built-up (m²) | 7,505.03 | |
| Towers | 0 | |
| Units | 60 | |
| Booked | 60 |
Unit types
| Type | Units | Booked | Tower |
|---|---|---|---|
| 2BHK | 60 | 60 | FINSBURY PARK |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 99% | |
|---|---|---|
| As of | 2023-10-20 | |
| Start | 2022-10-27 | |
| Proposed completion | 2027-02-27 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
| 2025-2026 Q1 |
| 2025-2026 Q2 |
| 2025-2026 Q3 |
| 2025-2026 Q4 |
| 2024-2025 Q1 |
| 2024-2025 Q2 |
| 2024-2025 Q3 |
| 2024-2025 Q4 |
| 2023-2024 Q4 |
| 2023-2024 Q1 |
| 2023-2024 Q2 |
| 2023-2024 Q3 |
| 2022-2023 Q3 |
| 2022-2023 Q4 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | REIGATEBUILDERSPRIVATELIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | SBI | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/11116
- https://rera.kerala.gov.in/projects?district=591&page=6
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=Z6iXPkBjPzdJ2uuY%2F3dRNZtpbALxYeEIqabRX1sdw3FOfpQxSTlKeCTWi4hogS6pmJNU7cR7iBua6xbXk%2FLzadbVFLWH8X04B32easRS9Jx44%2B1TDXgwb343OUpE40vd6fH2HstQpv3gqMiQaKFTz24HDHR8VFqVWOODGT4%2FDwom0NxS15a0Ew%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=11116&Division=1&UserID=32260&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2022-11-03
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2022-10-19
- Copy of Valid Building Permit · 2022-10-19
- Detailed technical specifications to be adopted in the project · 2022-10-19 · Sign in to download
- Detailed technical specifications to be adopted in the project · 2022-10-19 · Sign in to download
- Layout approval plan · 2022-10-19
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2022-10-19 · Sign in to download
- Site Plan / Site Map · 2022-10-19
- Other · 2022-10-19 · Sign in to download
- Other · 2022-10-19 · Sign in to download
- Other · 2022-10-19 · Sign in to download
- Architect's Certificate in Form No 2 · 2022-10-19 · Sign in to download
- Engineer's Certificate in Form No 3 · 2022-10-19 · Sign in to download
- Consent to establish (Clearance from Pollution Control Board) · 2022-10-19 · Sign in to download
- Initial NOC from Fire and Rescue department · 2022-11-02
- Brochure / prospectus issued in regard to this project · 2022-10-19 · Sign in to download