Overview
RISHIKA CITY CENTRE
VARDAAN BUILDTECH PRIVATE LIMITED · Sonipat
Units182
Completion2030-03-31Proposed
Valid to2030-03-31
Approvals6
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 10 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 6 documents · 2 source links |
Registration
Registration
| Promoter | VARDAAN BUILDTECH PRIVATE LIMITED | |
|---|---|---|
| District | Sonipat | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-SNP-840-2026 | |
| Valid to | 2030-03-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2030-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | Allotment Letter by Municipal Council, Sonepat Memo No. 907 dated 19.05.2006. | Town & Country Planning Department | |
| Layout Plan | |||
| Building Plan | 2024-09-19 | ||
| I. REVISED BUILDING PLAN | 2024-09-19 | ||
| II. RE-ALLOTMENT LETTER FROM MUNICIPAL COUNCIL, SONIPAT | 2006-05-19 | ||
| III. DEED OF CONVEYANCE OF LAND BY MC SONIPAT AND VARDAAN BUILDTECH PVT. LTD. | 2017-01-24 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹45,68,00,000 | |
|---|---|---|
| Construction | ₹1,21,47,57,000 | |
| Total | ₹2,46,23,30,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 16,308.66 | |
|---|---|---|
| FAR | 200 | |
| Units | 182 |
Unit types
| Apartment/Shops/Other Buildings | 25.41 | 12 |
| Apartment/Shops/Other Buildings | 24.8 | 48 |
| Apartment/Shops/Other Buildings | 71.66 | 4 |
| Apartment/Shops/Other Buildings | 70.14 | 16 |
| Apartment/Shops/Other Buildings | 1,628.66 | 37 |
| Apartment/Shops/Other Buildings | 2,271.91 | 43 |
| Apartment/Shops/Other Buildings | 2,125.91 | 14 |
| Apartment/Shops/Other Buildings | 406.17 | 2 |
| Apartment/Shops/Other Buildings | 2,549.24 | 5 |
| Apartment/Shops/Other Buildings | 2,356.47 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-09-15 | |
|---|---|---|
| Proposed completion | 2030-03-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | VARDAAN BUILDTECH PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI BANK LIMITED | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/view_project/project_preview_open/3454
- Registration Certificate
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2025-09-11 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2025-09-11
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2025-09-11
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2025-09-11
- PAYMENT PLAN · 2026-01-29