Overview
RISHIKRISHNA RESIDENCY(ROW HOUSES)
RISHIKRISHNA BUILDERS PRIVATE LIMITED · Lucknow
Units38
Completion2020-10-03Revised · Proposed 2020-04-04
Registered on2017-08-15
Valid to2020-10-03
Approvals1
Complaints0As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 0 project complaints · 0 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 7 unit types |
| Construction & progress | 3 progress details · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 2 documents · 9 source links |
Registration
Registration
| Promoter | RISHIKRISHNA BUILDERS PRIVATE LIMITED | |
|---|---|---|
| District | Lucknow | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ11546 | |
| Registered on | 2017-08-15 | |
| Valid to | 2020-10-03 | |
| Project type | Residential | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2020-04-04 | |
| Revised completion | 2020-10-03 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | 1231/NAKSA/NI.VI./ZI.PA./2016-17 | 2017-03-04 | 2019-03-03 | Lucknow Development Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 0 | |
|---|---|---|
| Promoter | 0 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹7,60,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,528 | |
|---|---|---|
| Units | 38 |
Unit types
| Villa | 44 | 1 |
| Villa | 66 | 5 |
| Villa | 54 | 6 |
| Villa | 39 | 7 |
| Villa | 67 | 3 |
| Villa | 54 | 15 |
| Villa | 58 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-04-05 | |
|---|---|---|
| Proposed completion | 2020-04-04 | |
| Revised completion | 2020-10-03 |
Extensions
| Valid to | Reason |
|---|---|
| 2020-10-03 | Six months extension in view of force majeure caused by covid-19 pandemic |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RISHIKRISHNA BUILDERS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=j3QKGlCmT7w=&hfFlag=GL34ZTSSjlw=&NPJ6RAme=XoViquZVYrV939QrNZ2JXKMeMEG1Msqgf/S+z2S8t1yZNj9LZMBFEQ==&PaURJEMAN4=ZL9MNERkNda13YUWETSolA==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/WebService1.asmx/loadPlot_new
- https://up-rera.in/WebService1.asmx/loadVillasnew
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=LUCKNOW
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=j3QKGlCmT7w=
- Sanctioned Layout Plan (Of Entire Project) · 2017-08-15
- Authentic copy of Approval of Project · 2017-08-15