Overview
RISINGTON PHASE - II
SHREE MAHALAXMI ENTERPRISES · CHENNAI
Units1,332
Completion2032-02-19Proposed
Registered on2024-05-28
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Technical report | |
| Site & area | 3 site details · 6 unit types |
| Construction & progress | 1 progress detail · 2 quarters |
| Developer & finance | |
| Developer | 3 developer details · 4 professional firms |
| The evidence | |
| Sources | 18 documents · 7 source links |
Registration
Registration
| Promoter | SHREE MAHALAXMI ENTERPRISES | |
|---|---|---|
| District | Chennai | |
| Locality | CHENNAI | |
| Regulator | TNRERA | |
| Registration number | TN/29/Building/0379/2024 | |
| Registered on | 2024-05-28 | |
| Project type | Building | |
| Status (as filed) | Progress of Work as on June 2026 Extension given upto 29.06.2026 for Block-D, E1 and F | |
| Proposed completion | 2032-02-19 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Planning permission | CMDA/PP/HRB/S/0668/2022 | 2024-02-20 | 2032-02-19 | CMDA |
| Building permit | CEBA/WDCN15/00124/2024 | 2024-03-14 | GREATER CHENNAI CORPORATION |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 46,186 | |
|---|---|---|
| Towers | 5 | |
| Units | 1,332 |
Unit types
| Floor Area < 60 Sq.M | 0 | ||
| Floor Area > 60 Sq.M: | 171 | D | 19 |
| Floor Area < 60 Sq.M | 0 | ||
| Floor Area > 60 Sq.M: | 114 | E1 | 19 |
| Floor Area < 60 Sq.M | 162 | F | 18 |
| Floor Area > 60 Sq.M: | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2032-02-19 |
|---|
Quarterly progress
| Quarter |
|---|
| 2026-Q2 |
| 2026-Q2 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHREE MAHALAXMI ENTERPRISES | |
|---|---|---|
| Escrow bank | ICICI Bank | |
| Other projects in this city pack | 0 |
Professional firms
| Engineer | M/S GEO FOUNDATION & STRUCTURES Pvt. Ltd., |
| Engineer | MAHIMTURA Consultants Pvt. Ltd. |
| Architect | RSP DESIGN CONSULTANRS INDIA PVT LTD |
| Contractor | Facilities And Building Solutions Private Limited |
Sources
Sources
Source URLs & documents
- https://rera.tn.gov.in/project-details/beadc660-e83a-11ee-b10b-3515694a8e65
- https://rera.tn.gov.in/public-view1/building/pfirm/bea7c470-e83a-11ee-8b82-f313697f5807
- https://rera.tn.gov.in/public-view2/building/pfirm/04521120-e83f-11ee-b9f0-e51ef075d423
- https://rera.tn.gov.in/registered-building/tn
- Form-c
- Progress of Work as on June 2026
- Planning Permission Approval / Renewal Letter
- Approved Plan with Local Body Seal(Upload in Readable Format)
- Building Permit Letter
- Uploaded Document · Sign in to download
- Uploaded Document · Sign in to download
- Uploaded Document · Sign in to download
- Encumbrance Certificate from the date of approval of planning permission to RERA submission date
- Carpet Area Statement
- Soil Test Report (Mentioning the Site Address) · Sign in to download
- Structural Stability Certificate along with Structural Design Calculation (Indicating Site Address & No. of Floors as per Approved Plan)
- Design & Drawing for Structural Stability
- Declaration (Form B) · Sign in to download
- Stage of Construction & Site Photographs with date · Sign in to download
- Bank statement for the last one year duly signed by the Bank to be enclosed
- Furnish the details Flat-wise
- Promoter firm registration certificate · Sign in to download
- Planning permission · 2024-02-20
- Building permit · 2024-03-14
- 2026-Q2